| s/no. |
NAME OF PROJECT |
SUB-COUNTY |
WARD |
LOCATION |
DEPARTMENT |
SECTION |
CONTRACT SUM |
AMOUNT PAID |
BAL DUE TO CONTRACTOR |
STATUS |
NAME OF CONTRACTOR |
START DATE |
END DATE |
| 1 |
Construction of Sikata Boda Boda Shades |
KABUCHAI |
WEST NALONDO |
Sikata |
|
|
249,469.00 |
184,533.00 |
64,936.00 |
Complete |
|
|
|
| 2 |
Construction of Chebukwa Boda Boda Shades |
KABUCHAI |
WEST NALONDO |
Kabuchai |
|
|
249,469.00 |
184,533.00 |
64,936.00 |
Complete |
|
|
|
| 3 |
Construction of Nalondo Boda Boda Shade |
KABUCHAI |
WEST NALONDO |
Nalondo |
|
|
249,469.00 |
184,533.00 |
64,936.00 |
Complete |
|
|
|
| 4 |
Replacement of Ndicho Water pumb |
KABUCHAI |
WEST NALONDO |
Nalondo |
|
|
220,000.00 |
162,800.00 |
57,200.00 |
Complete |
|
|
|
| 5 |
Mantainance of Kasosi pri. Muyayi bridge |
KABUCHAI |
WEST NALONDO |
kasosi |
|
|
2,920,764.00 |
2,431,433.00 |
489,331.00 |
Complete |
|
|
|
| 6 |
Mantainance of Kabuchai mkt – Kabuchai pri. Rd |
KABUCHAI |
WEST NALONDO |
0 |
|
|
2,566,651.10 |
1,935,393.00 |
631,258.10 |
Complete |
|
|
|
| 7 |
Periodic maintenance of Sawali Primary Sch-Mabanga Seminary road |
KABUCHAI |
WEST NALONDO |
0 |
|
|
4,033,755.00 |
2,526,713.00 |
1,507,042.00 |
Complete |
|
|
|
| 8 |
Periodic maintenance of chemwa bridge – Nangwe-Muyayi road |
KABUCHAI |
WEST NALONDO |
0 |
|
|
5,698,616.00 |
3,645,588.00 |
2,053,028.00 |
Complete |
|
|
|
| 9 |
Kabuchai water project |
KABUCHAI |
WEST NALONDO |
0 |
|
|
– |
3,008,799.45 |
– |
Complete |
|
|
|
| 10 |
Drilling & equipping of 2no. Boreholes at Chemwa & Chebukwa mkts |
KABUCHAI |
WEST NALONDO |
0 |
|
|
– |
3,872,400.00 |
– |
Complete |
|
|
|
| 11 |
Erection and completion of Nalondo health centre and chemwa bridge dispensary |
KABUCHAI |
WEST NALONDO |
Nalondo/ Chemwa |
|
|
5,862,691.00 |
– |
5,862,691.00 |
Complete |
|
|
|
| 12 |
Construction of borehole and installation of water pump |
KABUCHAI |
WEST NALONDO |
0 |
|
|
4,307,065.00 |
2,584,239.00 |
1,722,826.00 |
Complete |
|
|
|
| 13 |
Street lights at Busiraka, Nabende, Chebukwa,Kabuchai and Sirare |
KABUCHAI |
WEST NALONDO |
Busiraka,chebukwa,sirare, nabende and Busiraka |
|
|
– |
– |
– |
Complete |
|
|
|
| 14 |
construction of tower tank steel brazed 50M3 9m tower and 2 water kiosks of 5000 liters and electric/solar pump |
KABUCHAI |
WEST NALONDO |
Sirare primary 2. Nangwe primary |
|
|
– |
– |
– |
Complete |
|
|
|
| 15 |
Masonry tank 50m3 & 2 water kiosks of 5000 liters and eletric pump |
KABUCHAI |
WEST NALONDO |
Musokho Secondary |
|
|
– |
– |
– |
Complete |
|
|
|
| 16 |
construction of ECDE Classroom at Sikata primary |
KABUCHAI |
WEST NALONDO |
Sikata |
|
|
– |
– |
– |
Complete |
|
|
|
| 17 |
purchase of 01 acre piece of land for construction of Nabende ECDE |
KABUCHAI |
WEST NALONDO |
Nabende |
|
|
– |
– |
– |
Complete |
|
|
|
| 18 |
Piped water – Motherland-Tindibale-Chewangoi line |
MT. ELGON |
CHEPYUK |
kipsigon |
|
|
940,000.00 |
940,000.00 |
– |
Complete |
|
|
|
| 19 |
Street lights at Kaboriot 2, Huruma 3, Kabura2,Tindibare1, Makutano2. and Chepyuk 2. |
MT. ELGON |
CHEPYUK |
0 |
|
|
4,107,623.00 |
3,882,262.00 |
225,361.00 |
Complete |
|
|
|
| 20 |
Construction of Emia box culvert |
MT. ELGON |
CHEPYUK |
0 |
|
|
5,994,010.00 |
3,296,865.98 |
2,697,144.02 |
Complete |
|
|
|
| 21 |
Erection and completion of Chepkurkur Dispensary |
MT. ELGON |
CHEPYUK |
0 |
|
|
6,856,000.00 |
– |
– |
Complete |
|
|
|
| 22 |
Erection and completion of out patient unit at Chepyuk dispensary and Kaimagul dispensary |
MT. ELGON |
CHEPYUK |
Chepyuk/Kaimagul |
|
|
9,971,945.76 |
– |
– |
Complete |
|
|
|
| 23 |
Proposed erection and completion of 1NO. classroom at Somotwet, kapkong ,saria and serek primary school. |
MT. ELGON |
CHEPYUK |
Somotwet/Kapkong/Saria/Serek |
|
|
– |
– |
– |
Complete |
|
|
|
| 24 |
Construction of 02 ECDE Classrooms at Soet, and Kabukwo, |
MT. ELGON |
CHEPYUK |
Soet/Kabukwo |
|
|
– |
– |
– |
Complete |
|
|
|
| 25 |
Construction of Kimurio Bridge |
MT. ELGON |
CHEPYUK |
Kimurio |
|
|
– |
– |
– |
Complete |
|
|
|
| 26 |
Protection of 2 Wemwa water spring |
BUMULA |
KABULA |
Wemwa |
|
|
195,000.00 |
195,000.00 |
– |
Complete |
|
|
|
| 27 |
Protection of 2 Syoya water spring |
BUMULA |
KABULA |
Kabula |
|
|
195,000.00 |
195,000.00 |
– |
Complete |
|
|
|
| 28 |
Protection of 2 Wamumali water spring |
BUMULA |
KABULA |
Kabula |
|
|
195,000.00 |
195,000.00 |
– |
Complete |
|
|
|
| 29 |
Protection of 2 Naburereya water spring |
BUMULA |
KABULA |
Naburereya |
|
|
195,000.00 |
195,000.00 |
– |
Complete |
|
|
|
| 30 |
Protection of Talitia water spring |
BUMULA |
KABULA |
Talitia |
|
|
97,500.00 |
97,500.00 |
– |
Complete |
|
|
|
| 31 |
Protection of 1 malinda water spring |
BUMULA |
KABULA |
Malinda |
|
|
97,500.00 |
97,500.00 |
– |
Complete |
|
|
|
| 32 |
Proposed erection & completion of ECDE Classroom at Syoya market |
BUMULA |
KABULA |
Syoya mkt |
|
|
1,215,761.00 |
1,055,615.00 |
160,146.00 |
Complete |
|
|
|
| 33 |
Construction of ECDE Classroom at Bukumuma |
BUMULA |
KABULA |
Bumukama pri |
|
|
1,191,317.68 |
833,513.00 |
357,804.68 |
Complete |
|
|
|
| 34 |
Construction of Watoya market – Lukusi pri. Rd |
BUMULA |
KABULA |
0 |
|
|
3,227,004.00 |
2,218,702.00 |
1,008,302.00 |
Complete |
|
|
|
| 35 |
Periodic Maintenance of Elim wells academy- Tarmac kabula catholic Road |
BUMULA |
KABULA |
0 |
|
|
4,142,985.00 |
3,068,179.05 |
1,074,805.95 |
Complete |
|
|
|
| 36 |
School empowerment programme |
BUMULA |
KABULA |
0 |
|
|
1,101,000.00 |
1,101,000.00 |
– |
Complete |
|
|
|
| 37 |
Periodic Maintenance of Syoya market – Chiefs home Road |
BUMULA |
KABULA |
0 |
|
|
3,214,244.00 |
2,244,772.00 |
969,472.00 |
Complete |
|
|
|
| 38 |
Periodic Maintenance of Mukhuma-Bukumuma road |
BUMULA |
KABULA |
0 |
|
|
4,887,080.00 |
3,695,413.00 |
1,191,667.00 |
Complete |
|
|
|
| 39 |
Peridic maintenance of roads in Kabula ward(Samichi Rd2.1km,Kabula-Wamumali Rd1.8km) |
BUMULA |
KABULA |
Kabula |
|
|
5,230,579.00 |
– |
– |
Complete |
|
|
|
| 40 |
Purchase of land for Kabula dispensary |
BUMULA |
KABULA |
kabula |
|
|
1,450,000.00 |
– |
– |
0 |
|
|
|
| 41 |
Protection of 4 Water spring |
BUMULA |
KABULA |
Kabula |
|
|
3,986,000.00 |
– |
– |
Complete |
|
|
|
| 42 |
Construction of Boda boda sheds at Babula,Watoya and Malinda market |
BUMULA |
KABULA |
kabula,watoya,malinda |
|
|
3,014,341.20 |
– |
– |
Complete |
|
|
|
| 43 |
ONSTRUCTION OF 01 NO. ECDE CLASSROOM AT LUKUSI PRIMARY AND CONSTRUCTION OF 01 WORKSHOP AT KABULA VTC |
BUMULA |
KABULA |
Kabula/Lukusi primary |
|
|
3,574,100.00 |
– |
– |
Complete |
|
|
|
| 44 |
Periodic maintenance of Malinda Primary- Samichi River Road- Wamunyiri Road |
BUMULA |
KABULA |
Kabula |
|
|
– |
– |
– |
Complete |
|
|
|
| 45 |
Main Road-Naburerey Namasanda Road |
BUMULA |
KABULA |
kabula |
|
|
– |
– |
– |
Complete |
|
|
|
| 46 |
Protection of okamo water spring |
TONGAREN |
MBAKALO |
Okamo |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 47 |
Protection ofMucharia water spring |
TONGAREN |
MBAKALO |
Mucharia |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 48 |
Protection of Malavawater spring |
TONGAREN |
MBAKALO |
Malava |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 49 |
Protection of Sibembe water spring |
TONGAREN |
MBAKALO |
Sibembe |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 50 |
Protection of Kamili water spring |
TONGAREN |
MBAKALO |
Kamili |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 51 |
Protection of Pongokha water spring |
TONGAREN |
MBAKALO |
Pongokha |
|
|
145,015.00 |
145,015.00 |
– |
Complete |
|
|
|
| 52 |
community water project |
TONGAREN |
MBAKALO |
Mbakalo |
|
|
9,001,047.75 |
7,365,340.00 |
4,201,047.75 |
complete |
|
|
|
| 53 |
Construction of 3no. Culverts |
TONGAREN |
MBAKALO |
kikechi |
|
|
1,312,699.00 |
817,597.00 |
495,102.00 |
Complete |
|
|
|
| 54 |
installation of street lights |
TONGAREN |
MBAKALO |
Luuya,Kibisi,Makunga,Karima |
|
|
4,800,000.00 |
4,800,000.00 |
– |
complete |
|
|
|
| 55 |
Construction of Makunga dispensary and Karima dispensary maternity ward |
TONGAREN |
MBAKALO |
Makunga, Karima |
|
|
3,939,580.00 |
– |
– |
Complete |
|
|
|
| 56 |
Machami water project |
TONGAREN |
MBAKALO |
0 |
|
|
6,621,716.00 |
– |
– |
Complete |
|
|
|
| 57 |
Purchase of 1 acre for Musembe dispensary |
TONGAREN |
MBAKALO |
Musembe |
|
|
2,200,000.00 |
– |
– |
Complete |
|
|
|
| 58 |
Construction of 4 ECDE classrooms |
TONGAREN |
MBAKALO |
Musembe,Liyuke,Musokho,Lumukile |
|
|
– |
– |
– |
Complete |
|
|
|
| 59 |
Construction musembe vocational training institute |
TONGAREN |
MBAKALO |
Musembe |
|
|
– |
– |
– |
Complete |
|
|
|
| 60 |
installation of culverts |
TONGAREN |
MBAKALO |
mbakalo |
|
|
– |
– |
– |
Complete |
|
|
|
| 61 |
Construction of phase 1 Naitiri dispensary |
TONGAREN |
MBAKALO |
Naitiri |
|
|
– |
– |
– |
Complete |
|
|
|
| 62 |
Construction of bodaboda shed |
TONGAREN |
MBAKALO |
Mitelwa,Kibisi,Nzoia,Mbakalo,Karima,Makunga,Nabiswa,Nyange |
|
|
– |
– |
– |
Complete |
|
|
|
| 63 |
Construction of phase 2 o makunga dispensary |
TONGAREN |
MBAKALO |
Makunga |
|
|
– |
– |
– |
0 |
|
|
|
| 64 |
Construction of Classrooms at Mukwa Polytechnic |
BUMULA |
SIBOTI |
Mukwa |
|
|
900,000.00 |
900,000.00 |
– |
Complete |
|
|
|
| 65 |
Purchase of 2 acres of land for kisawayi dispensary |
BUMULA |
SIBOTI |
Kisawayi |
|
|
1,400,000.00 |
1,400,000.00 |
– |
Complete |
|
|
|
| 66 |
Drilling and equiping of a bore hole at siboti health centre |
BUMULA |
SIBOTI |
siboti |
|
|
1,940,000.00 |
1,494,955.00 |
445,045.00 |
Complete |
|
|
|
| 67 |
Periodic Maintenance of masielo- r.kimwanga-siboti pri. Road |
BUMULA |
SIBOTI |
0 |
|
|
4,658,931.00 |
3,981,489.00 |
677,442.00 |
Complete |
|
|
|
| 68 |
Periodic mantainance of Miluki- Namanje- Bisuche – R.Toloso road |
BUMULA |
SIBOTI |
Miluki- Namanje- Bisuche – R.Toloso |
|
|
7,928,600.00 |
6,379,160.00 |
1,549,440.00 |
Complete |
|
|
|
| 69 |
Drilling & equiping of 2 no. boreholes at Manani pri. & Nasimbo pri. |
BUMULA |
SIBOTI |
Manani pri. & Nasimbo pri |
|
|
2,399,250.00 |
1,963,248.00 |
436,002.00 |
Complete |
|
|
|
| 70 |
Drilling & equiping of boreholes at Kitayi pri. |
BUMULA |
SIBOTI |
Kitayi Pri. |
|
|
1,199,625.00 |
981,624.00 |
218,001.00 |
Complete |
|
|
|
| 71 |
periodic maintenance of roads in Siboti ward(Wekesa lazaro-namuninge river road 2.25km,mukwa-namanje-bosio road 4.0km ) |
BUMULA |
SIBOTI |
siboti |
|
|
10,600,863.00 |
– |
– |
Complete |
|
|
|
| 72 |
construction of Kisawayi dispensary |
BUMULA |
SIBOTI |
Kisawyi |
|
|
– |
– |
– |
Complete |
|
|
|
| 73 |
Drilling of Bisuche borehole |
BUMULA |
SIBOTI |
0 |
|
|
1,923,800.00 |
– |
– |
Complete |
|
|
|
| 74 |
Construction of 3no classrooms |
BUMULA |
SIBOTI |
Namanje,Napara ACK,Lurare primary |
|
|
2,801,140.00 |
– |
– |
Complete |
|
|
|
| 75 |
Grading and gravelling of Miluki- Kabubero(2KM) |
BUMULA |
SIBOTI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 76 |
Construction of ecde classroom at Musakasa primary |
BUMULA |
SIBOTI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 77 |
Renovation of Machwele Youth Polytechnic |
BUMULA |
SIBOTI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 78 |
sinking of 6 shallow wells |
BUMULA |
SIBOTI |
Manani,Kikwechi,Kabubero,Sirende,Musakasa,Nangoli |
|
|
– |
– |
– |
Complete |
|
|
|
| 79 |
Construction of Cheptais Boda-Boda Shade |
MT. ELGON |
CHEPTAIS |
Cheptais |
|
|
218,110.00 |
218,110.00 |
– |
Complete |
|
|
|
| 80 |
Construction of Chepkube Boda-Boda shade |
MT. ELGON |
CHEPTAIS |
Chepkube |
|
|
218,110.00 |
218,110.00 |
– |
Complete |
|
|
|
| 81 |
Construction of Shoe shiners at Cheptais |
MT. ELGON |
CHEPTAIS |
Cheptais |
|
|
193,800.00 |
193,800.00 |
– |
Complete |
|
|
|
| 82 |
Rehabilitation of public toilets at Cheptais town |
MT. ELGON |
CHEPTAIS |
Cheptais |
|
|
282,842.00 |
282,842.00 |
– |
Complete |
|
|
|
| 83 |
Acquisition of land- NALONDO DISPENSARY |
MT. ELGON |
CHEPTAIS |
cheptais |
|
|
460,000.00 |
230,000.00 |
– |
Complete |
|
|
|
| 84 |
Acquisition of land-BULUKHA ECDE |
MT. ELGON |
CHEPTAIS |
Malakisi |
|
|
200,000.00 |
200,000.00 |
– |
Complete |
|
|
|
| 85 |
Acquisition of land-KAMATA ECDE |
MT. ELGON |
CHEPTAIS |
Malakisi |
|
|
362,000.00 |
362,000.00 |
– |
Complete |
|
|
|
| 86 |
Acquisition of land- NALONDO DISPENSARY |
MT. ELGON |
CHEPTAIS |
cheptais |
|
|
230,000.00 |
230,000.00 |
– |
Complete |
|
|
|
| 87 |
Acquisition of land for Kimaswa dispensary |
MT. ELGON |
CHEPTAIS |
cheptais |
|
|
489,000.00 |
489,000.00 |
– |
Complete |
|
|
|
| 88 |
Periodic mantainance of Kimaswa- Chemuses road |
MT. ELGON |
CHEPTAIS |
Kimaswa-Chemuses |
|
|
5,641,575.00 |
3,479,705.00 |
2,161,870.00 |
Complete |
|
|
|
| 89 |
Proposed erection and completion of out patient dpt of Chebwek dispensary |
MT. ELGON |
CHEPTAIS |
Chebwek |
|
|
13,191,212.00 |
2,299,788.00 |
10,891,424.00 |
complete |
|
|
|
| 90 |
Peridic maintenance of roads in Cheptais ward |
MT. ELGON |
CHEPTAIS |
Cheptais |
|
|
8,166,690.00 |
– |
– |
Complete |
|
|
|
| 91 |
Purchase of 1 acre for Rama E.C.D.E |
MT. ELGON |
CHEPTAIS |
Rama |
|
|
500,000.00 |
– |
500,000.00 |
Complete |
|
|
|
| 92 |
Purchase of 1 acre for Chenomor coffee factory |
MT. ELGON |
CHEPTAIS |
Chenomor |
|
|
500,000.00 |
– |
500,000.00 |
Complete |
|
|
|
| 93 |
proposed completion of septic tank |
MT. ELGON |
CHEPTAIS |
cheptais market |
|
|
492,269.20 |
– |
492,269.20 |
Complete |
|
|
|
| 94 |
Construction of a Maternity Ward |
MT. ELGON |
CHEPTAIS |
Cheptais |
|
|
– |
– |
– |
Complete |
|
|
|
| 95 |
Construction of a Dispensary at Nalondo |
MT. ELGON |
CHEPTAIS |
Nalondo |
|
|
– |
– |
– |
Complete |
|
|
|
| 96 |
periodic maintenance of Chepkube-FCS-Chebwek-Cheptoror |
MT. ELGON |
CHEPTAIS |
cheptais |
|
|
– |
– |
– |
Complete |
|
|
|
| 97 |
Extension of piped water from Musikoma community water- Samoya sec. School |
KANDUYI |
MUSIKOMA |
Musikoma |
|
|
955,434.00 |
955,434.00 |
– |
Complete |
|
|
|
| 98 |
Construction of Kisule shallow wells |
KANDUYI |
MUSIKOMA |
Kisule |
|
|
149,738.00 |
134,764.20 |
14,973.80 |
Complete |
|
|
|
| 99 |
Purchase of land for Sacred ECDE |
KANDUYI |
MUSIKOMA |
Siritanyi |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 100 |
construction of Tulienge -Namasanda Road |
KANDUYI |
MUSIKOMA |
Tulienge |
|
|
2,269,064.00 |
1,837,942.00 |
431,122.00 |
Complete |
|
|
|
| 101 |
Grading gravelling of Walala – Samoya road |
KANDUYI |
MUSIKOMA |
Walala-Samoya |
|
|
7,870,716.00 |
6,282,206.00 |
1,588,510.00 |
Complete |
|
|
|
| 102 |
Grading, gravelling of Namisi Ng’oli – Siloba road |
KANDUYI |
MUSIKOMA |
Ng’oli-Siloba |
|
|
9,125,256.00 |
8,074,209.00 |
1,051,047.00 |
Complete |
|
|
|
| 103 |
Peridic maintenance of roads in Musikoma ward(Oldrex-Sio Rd1.0km) |
KANDUYI |
MUSIKOMA |
0 |
|
|
2,502,502.80 |
– |
– |
Complete |
|
|
|
| 104 |
construction and completion of Siritanyi dispensary |
KANDUYI |
MUSIKOMA |
Siritanyi |
|
|
3,980,528.40 |
– |
– |
Complete |
|
|
|
| 105 |
Construction and protection of 5no water spring |
KANDUYI |
MUSIKOMA |
0 |
|
|
978,500.00 |
– |
– |
Complete |
|
|
|
| 106 |
Construction of ECDE Classroom at namisi |
KANDUYI |
MUSIKOMA |
Namisi |
|
|
– |
– |
– |
Complete |
|
|
|
| 107 |
Installation of streetlights |
KANDUYI |
MUSIKOMA |
Sio- Oldrex |
|
|
– |
– |
– |
Complete |
|
|
|
| 108 |
Grading, gravelling and culverting of Mulaha- Sio road |
KANDUYI |
MUSIKOMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 109 |
construction of ECDE Classroom at Namasanda |
KANDUYI |
MUSIKOMA |
Namasanda |
|
|
– |
– |
– |
Complete |
|
|
|
| 110 |
Drilling & Equiping Jordan opharnage home |
KANDUYI |
MUSIKOMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 111 |
Protection of Mukonambi water springs |
KANDUYI |
WEST SANG’ALO |
Mukonambi |
|
|
131,000.00 |
113,970.00 |
17,030.00 |
Complete |
|
|
|
| 112 |
Protection ofNamaanga Water spring |
KANDUYI |
WEST SANG’ALO |
Namaanga |
|
|
131,000.00 |
113,970.00 |
17,030.00 |
0 |
|
|
|
| 113 |
Protection of nasianda Water spring |
KANDUYI |
WEST SANG’ALO |
Nasianda |
|
|
144,625.00 |
125,823.50 |
18,801.50 |
Complete |
|
|
|
| 114 |
Protection of Makanyaka Water spring |
KANDUYI |
WEST SANG’ALO |
Sang’alo |
|
|
144,625.00 |
125,823.50 |
18,801.50 |
0 |
|
|
|
| 115 |
Protection of Namikelo Water spring |
KANDUYI |
WEST SANG’ALO |
Namikelo |
|
|
147,440.00 |
128,272.50 |
19,167.50 |
Complete |
|
|
|
| 116 |
Protection of Telwa Water spring |
KANDUYI |
WEST SANG’ALO |
Telwa |
|
|
147,440.00 |
125,272.50 |
22,167.50 |
0 |
|
|
|
| 117 |
Construction of kacombo bridge |
KANDUYI |
WEST SANG’ALO |
Kachombo |
|
|
1,999,993.50 |
1,835,567.90 |
164,425.60 |
Complete |
|
|
|
| 118 |
Construction and protection of Miendo water spring |
KANDUYI |
WEST SANG’ALO |
Miendo |
|
|
150,000.00 |
150,000.00 |
– |
Complete |
|
|
|
| 119 |
Construction and protection of Hossen water springs |
KANDUYI |
WEST SANG’ALO |
Hossen |
|
|
150,000.00 |
150,000.00 |
– |
Complete |
|
|
|
| 120 |
Construction and protection of Mwepole water springs |
KANDUYI |
WEST SANG’ALO |
Mwepole |
|
|
150,000.00 |
150,000.00 |
– |
Complete |
|
|
|
| 121 |
Construction and protection of Okumu water spring |
KANDUYI |
WEST SANG’ALO |
Okumu |
|
|
– |
– |
– |
complete |
|
|
|
| 122 |
Periodic mantainance of Bulondo – Musamba road |
KANDUYI |
WEST SANG’ALO |
Bulondo – Musamba |
|
|
8,593,222.00 |
4,530,050.00 |
4,063,172.00 |
Complete |
|
|
|
| 123 |
Peridic maintenance of roads in West Sang’alo ward(Luyekhe-Namwacha Rd3.0KM) |
KANDUYI |
WEST SANG’ALO |
Luyekhe- Namwacha |
|
|
3,816,968.00 |
– |
– |
Complete |
|
|
|
| 124 |
Completion of Bulondo dispensary |
KANDUYI |
WEST SANG’ALO |
Bulondo |
|
|
– |
– |
– |
Complete |
|
|
|
| 125 |
Drilling of a borehole and installation of a pump |
KANDUYI |
WEST SANG’ALO |
0 |
|
|
1,192,400.00 |
– |
1,192,400.00 |
Complete |
|
|
|
| 126 |
Construction of 2no ECDE Classrroom |
KANDUYI |
WEST SANG’ALO |
Siange and Kamba primary |
|
|
3,364,200.00 |
– |
– |
Complete |
|
|
|
| 127 |
Purchase of 1 acre for Ndakaru E.C.D.E |
KANDUYI |
WEST SANG’ALO |
Ndakaru |
|
|
350,000.00 |
– |
– |
Complete |
|
|
|
| 128 |
Rehabilitation of kitinda and Chemululuchi cattle dips |
KANDUYI |
WEST SANG’ALO |
Chemululuchi |
|
|
– |
– |
– |
Complete |
|
|
|
| 129 |
Professor Junction Road- Namwacha Market-Krato Junction 2km |
KANDUYI |
WEST SANG’ALO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 130 |
Construction of Culvert at Chemuluchi river |
KANDUYI |
WEST SANG’ALO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 131 |
usweti-Sang’alo junction -Khalaba river road |
KANDUYI |
WEST SANG’ALO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 132 |
Drilling and equipping of a borehole at Sang’alo ,market |
KANDUYI |
WEST SANG’ALO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 133 |
Construction of Boda-boda Shade at Khalamuli |
WEBUYE EAST |
SITIKHO |
Khalamuli |
|
|
245,862.00 |
245,862.00 |
– |
Complete |
|
|
|
| 134 |
Construction of Boda-boda Shade at Milo |
WEBUYE EAST |
SITIKHO |
Milo |
|
|
199,148.00 |
199,148.00 |
– |
Complete |
|
|
|
| 135 |
Construction of Boda-boda Shade at Sitikho |
WEBUYE EAST |
SITIKHO |
Sitikho |
|
|
245,862.00 |
245,862.00 |
– |
Complete |
|
|
|
| 136 |
Erection and completion of Administrative block for Sitikho Vocati. Training |
WEBUYE EAST |
SITIKHO |
0 |
|
|
3,018,042.00 |
2,023,656.00 |
994,386.00 |
complete |
|
|
|
| 137 |
Periodic mantainance of Ngachi-Muchi- R.Nabwala Lufwindiri road |
WEBUYE EAST |
SITIKHO |
Ngachi-Muchi- R.Nabwala Lufwindiri |
|
|
8,678,565.00 |
6,465,012.00 |
2,213,553.00 |
Complete |
|
|
|
| 138 |
Peridic maintenance of roads in Sitikho ward(khalala friends church-musabale-sitikho mkt road2.0km,Ngwelo pri-Mangoli-Kwabwabi river road1.35km) |
WEBUYE EAST |
SITIKHO |
0 |
|
|
10,336,800.60 |
– |
– |
Complete |
|
|
|
| 139 |
Construction of Mangana dispensary |
WEBUYE EAST |
SITIKHO |
0 |
|
|
3,000,000.00 |
– |
3,000,000.00 |
Complete |
|
|
|
| 140 |
Construction of 5NO water spring |
WEBUYE EAST |
SITIKHO |
0 |
|
|
996,700.00 |
– |
996,700.00 |
0 |
|
|
|
| 141 |
Construction of 1no Classroom at mukite primary |
WEBUYE EAST |
SITIKHO |
Mukite primary |
|
|
1,287,120.00 |
– |
1,287,120.00 |
Complete |
|
|
|
| 142 |
Yalusi SA CHURCH- little angel bridge- justo- Chiefs center 2km |
WEBUYE EAST |
SITIKHO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 143 |
Kuywa SA church – kuywa Primary- mujukuwa PCU – Wandili junction road 2.5km |
WEBUYE EAST |
SITIKHO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 144 |
Ngwelo primary-Philipo- Tela-simiyu-railway line road 2.5 km |
WEBUYE EAST |
SITIKHO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 145 |
Construction of Ngachi ECDE primary |
WEBUYE EAST |
SITIKHO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 146 |
Renovation of Mwumo Dispensary |
BUMULA |
WEST BUKUSU |
Mwumo |
|
|
969,600.00 |
893,269.00 |
76,331.00 |
Complete |
|
|
|
| 147 |
drilling and equiping of a bore hole at mayanja kibuke market |
BUMULA |
WEST BUKUSU |
mayanja |
|
|
1,909,950.00 |
1,662,912.00 |
247,038.00 |
Complete |
|
|
|
| 148 |
Grading & Gravelling of Marofu-Kisyoi-Busolo road |
BUMULA |
WEST BUKUSU |
Marofu-Kisyoi-Busolo |
|
|
1,685,276.00 |
1,449,968.00 |
235,308.00 |
Complete |
|
|
|
| 149 |
Periodic mantainance of Javan- luketelo tembo kihara road |
BUMULA |
WEST BUKUSU |
Javan- luketelo tembo kihara |
|
|
12,202,232.00 |
10,066,096.00 |
2,136,136.00 |
Complete |
|
|
|
| 150 |
Periodic mantainance of Lwanja – Kimwanga road |
BUMULA |
WEST BUKUSU |
Lwanja-Kimwanga |
|
|
2,947,560.00 |
2,402,331.42 |
545,228.58 |
Complete |
|
|
|
| 151 |
Drilling of boreholes at Tunya and Ksiyo |
BUMULA |
WEST BUKUSU |
tunya kisyoi |
|
|
3,730,100.00 |
– |
– |
Complete |
|
|
|
| 152 |
Drilling of Machwele borehole |
BUMULA |
WEST BUKUSU |
machwele |
|
|
1,907,400.00 |
– |
– |
Complete |
|
|
|
| 153 |
Construction of 2NO classroom at Lwanja and Ngoli primary |
BUMULA |
WEST BUKUSU |
0 |
|
|
1,938,120.00 |
– |
– |
Complete |
|
|
|
| 154 |
Purchase of 1 acre for Kimwanga market |
BUMULA |
WEST BUKUSU |
Kimwanga |
|
|
1,500,000.00 |
– |
– |
Complete |
|
|
|
| 155 |
onstruction of 2 NO door pit latrines |
BUMULA |
WEST BUKUSU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 156 |
Grading and gravelling of Ng’oli-Tulumba 2.5 |
BUMULA |
WEST BUKUSU |
west bukusu |
|
|
– |
– |
– |
Complete |
|
|
|
| 157 |
Grading and gravelling of Tarmac -Mm randa-selverio- Tunya 3 km |
BUMULA |
WEST BUKUSU |
west bukusu |
|
|
– |
– |
– |
Complete |
|
|
|
| 158 |
Construction of C33-Mukhaweli primary school road |
KANDUYI |
KHALABA |
mukhaweli |
|
|
909,440.00 |
816,531.00 |
92,909.00 |
Complete |
|
|
|
| 159 |
Mantainance of Pamus R. Khalaba road Nakumati R.Khalaba rd |
KANDUYI |
KHALABA |
Pamus |
|
|
5,037,648.00 |
3,585,100.00 |
1,452,548.00 |
Complete |
|
|
|
| 160 |
Periodic mantainance of A104 Total -Kanduyi Red Cross Namuyemba road 2km |
KANDUYI |
KHALABA |
A104 Total -Kanduyi Red Cross Namuyemba |
|
|
4,087,608.00 |
2,649,090.00 |
1,438,518.00 |
Complete |
|
|
|
| 161 |
mantainance of C33 countryside – marell Namuyemba Road |
KANDUYI |
KHALABA |
C33 countryside – marell Namuyemba |
|
|
6,336,036.00 |
3,745,474.00 |
2,590,562.00 |
Complete |
|
|
|
| 162 |
mantainance of C33 Village inn-R.khalaba Road |
KANDUYI |
KHALABA |
C33 Village inn-R.khalaba |
|
|
4,735,581.08 |
3,891,950.00 |
843,631.08 |
Complete |
|
|
|
| 163 |
Peridic maintenance of roads in Khalaba ward(mother kelvin road 0.8km,maina friends tentstar road 0.8km,c33-IGCroad 0.75km,C33-Sunrise road 1.1km,C33-Chetambe road 1.2km,C33-King jesus road 0.7km) |
KANDUYI |
KHALABA |
kKhalaba |
|
|
13,649,882.40 |
– |
13,649,882.40 |
Complete |
|
|
|
| 164 |
Construction of Khalaba NZOWASCO pipeline water project |
KANDUYI |
KHALABA |
Khalaba |
|
|
2,358,300.00 |
– |
2,358,300.00 |
Complete |
|
|
|
| 165 |
Grading, gravelling and installation of culverts(800 M) at C33 Chepkube Market River Khalaba Road |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 166 |
Grading, gravelling and installation of culverts(800M) at C33 Pork Butchery-River Khalaba |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 167 |
Grading, gravelling and installation of culverts(700M) at C33 Mwatikho to River Khalaba Road |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 168 |
Grading, gravelling and installation of culverts(700M) Mija Road |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 169 |
C33 Grading, gravelling and installation of culverts(1KM) at Wandiaka – Juma Bakari Road |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 170 |
C33 Grading, gravelling and installation of culverts (800M) at ST Domiano Road |
KANDUYI |
KHALABA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 171 |
Protection of Mulaku water springs |
WEBUYE WEST |
NDIVISI |
mulaku |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 172 |
Protection of Chebukora water springs |
WEBUYE WEST |
NDIVISI |
Chebukora |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 173 |
Protection of Wechuli water springs |
WEBUYE WEST |
NDIVISI |
ndivisi |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 174 |
Protection of Wekhuyi water springs |
WEBUYE WEST |
NDIVISI |
Wekhuyi |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 175 |
Protection of Mbongi water springs |
WEBUYE WEST |
NDIVISI |
ndivisi |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 176 |
Protection of Stinii water springs |
WEBUYE WEST |
NDIVISI |
Stinii |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 177 |
Protection of Mitikuyu water springs |
WEBUYE WEST |
NDIVISI |
Mitikuyu |
|
|
142,000.00 |
142,000.00 |
– |
Complete |
|
|
|
| 178 |
Construction of Chebukola Culvert |
WEBUYE WEST |
NDIVISI |
chebukola |
|
|
1,754,500.00 |
1,297,211.76 |
457,288.24 |
Complete |
|
|
|
| 179 |
Construction of Mashebebe Culvert |
WEBUYE WEST |
NDIVISI |
mashebebe |
|
|
1,884,652.00 |
1,393,558.34 |
491,093.66 |
Complete |
|
|
|
| 180 |
Periodic maintenance of Wafula Munyereti -Ndivisi Girls High School road |
WEBUYE WEST |
NDIVISI |
Wafula Munyereti -Ndivisi Girls High |
|
|
5,150,116.12 |
3,843,226.00 |
1,306,890.12 |
Complete |
|
|
|
| 181 |
Periodic maintenance of john kiberenge -ondoti primary school road |
WEBUYE WEST |
NDIVISI |
john kiberenge -ondoti |
|
|
3,418,317.00 |
2,839,336.00 |
578,981.00 |
Complete |
|
|
|
| 182 |
Protection of Khahuta water springs |
WEBUYE WEST |
NDIVISI |
Khahuta |
|
|
147,840.00 |
100,778.00 |
47,062.00 |
Complete |
|
|
|
| 183 |
Construction of Boda-Boda shade at sinoko market |
WEBUYE WEST |
NDIVISI |
Sinoko Mkt |
|
|
196,132.80 |
160,490.00 |
35,642.80 |
Complete |
|
|
|
| 184 |
Periodic maintenance of ass. Chief – masibayi- khaoya dispensary road |
WEBUYE WEST |
NDIVISI |
ass. Chief – masibayi- khaoya dispensary |
|
|
2,967,902.00 |
2,530,742.00 |
437,160.00 |
Complete |
|
|
|
| 185 |
Proposed erection & completion of treatment rooms at Misemwa dispensary |
WEBUYE WEST |
NDIVISI |
Misemwa dispensary |
|
|
2,596,694.80 |
2,392,272.26 |
204,422.54 |
Complete |
|
|
|
| 186 |
Peridic maintenance of roads in Ndivisi ward(wabukhonyi-Makuselwa) |
WEBUYE WEST |
NDIVISI |
ndivisi |
|
|
7,958,168.40 |
– |
7,958,168.40 |
Complete |
|
|
|
| 187 |
Completion of Namwatikho dispensary and construction of 4door pit latrine at Sinoko dispensary |
WEBUYE WEST |
NDIVISI |
ndivisi |
|
|
– |
– |
– |
Complete |
|
|
|
| 188 |
Construction of 5NO water spring |
WEBUYE WEST |
NDIVISI |
0 |
|
|
697,488.00 |
– |
697,488.00 |
Complete |
|
|
|
| 189 |
Installation of solar powered highmast flood lights |
WEBUYE WEST |
NDIVISI |
ndivisi |
|
|
2,000,000.00 |
– |
2,000,000.00 |
Yet to Start |
|
|
|
| 190 |
Construction of 1no classroom at Sinoko primary |
WEBUYE WEST |
NDIVISI |
Sinoko pri |
|
|
1,360,670.00 |
– |
1,360,670.00 |
Complete |
|
|
|
| 191 |
proposed completion of 4 door pit latrines |
WEBUYE WEST |
NDIVISI |
0 |
|
|
800,000.00 |
– |
800,000.00 |
Complete |
|
|
|
| 192 |
Drilling and equiping of borehole at Namirembe dispensary |
WEBUYE WEST |
NDIVISI |
Dispensary |
|
|
– |
– |
– |
Complete |
|
|
|
| 193 |
Construction of 3NO Classroom at Katumi, Njata and Wandabwa |
WEBUYE WEST |
NDIVISI |
Katumi,Njata, Wandabwa |
|
|
– |
– |
– |
Complete |
|
|
|
| 194 |
Grading & Gravelling of Khakuta crossing road |
WEBUYE WEST |
NDIVISI |
Khakuta |
|
|
– |
– |
– |
Complete |
|
|
|
| 195 |
Grading & gravelling OF Masinde Benki- Kibisi River- Khaoya dispensary road 2km |
WEBUYE WEST |
NDIVISI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 196 |
Construction of Boda-Boda shade at Butonge |
BUMULA |
MALAKISI |
Butonge |
|
|
200,000.00 |
140,000.00 |
60,000.00 |
Complete |
|
|
|
| 197 |
Construction of bodaboda sheds |
BUMULA |
MALAKISI |
Namang’ofulo |
|
|
253,831.00 |
233,086.00 |
20,745.00 |
Complete |
|
|
|
| 198 |
Public Ecosan pit at Sirisia Market |
BUMULA |
MALAKISI |
Sirisia Market |
|
|
800,000.00 |
637,103.00 |
162,897.00 |
Complete |
|
|
|
| 199 |
Sirisia malinda bridge Culverts |
BUMULA |
MALAKISI |
Sirisia Malinda |
|
|
8,977,472.00 |
7,570,250.00 |
1,407,222.00 |
Complete |
|
|
|
| 200 |
Mantainance of Sirisia Wekelekha khalilo rd |
BUMULA |
MALAKISI |
0 |
|
|
3,501,344.00 |
3,098,798.00 |
402,546.00 |
Complete |
|
|
|
| 201 |
Erection and completion of Chongoyi ECDE C/room |
BUMULA |
MALAKISI |
Chongoyi |
|
|
1,287,460.00 |
817,854.00 |
469,606.00 |
Complete |
|
|
|
| 202 |
Bisunu public Latrine |
BUMULA |
MALAKISI |
Bisunu |
|
|
1,100,000.00 |
829,117.00 |
270,883.00 |
Complete |
|
|
|
| 203 |
Drilling of Kabaswana & Musieba pri. Borehole |
BUMULA |
MALAKISI |
Sirisia Wekelekha khalilo |
|
|
3,620,400.00 |
1,448,160.00 |
2,172,240.00 |
0 |
|
|
|
| 204 |
Peridic maintenance of roads in Malakisi south kulisiru ward(Chenjeni – Nabuloli road 3.6km) |
BUMULA |
MALAKISI |
0 |
|
|
4,277,616.00 |
– |
– |
Complete |
|
|
|
| 205 |
DRILLING OF SIBANDA AND NGALASIA BOREHOLES |
BUMULA |
MALAKISI |
0 |
|
|
3,749,120.00 |
– |
3,749,120.00 |
Complete |
|
|
|
| 206 |
DRILLING OF CHENJENI AND KULISIRU BOREHOLES |
BUMULA |
MALAKISI |
0 |
|
|
4,045,240.00 |
– |
– |
Complete |
|
|
|
| 207 |
DRILLING OF BUKOKHOLO BOREHOLE |
BUMULA |
MALAKISI |
0 |
|
|
2,058,480.00 |
– |
– |
Complete |
|
|
|
| 208 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AT NABULOOLI PRIMARY SCHOOL IN MALAKISI/KULISIRU WARD |
BUMULA |
MALAKISI |
0 |
|
|
2, 554,880 |
– |
2, 554,880 |
Complete |
|
|
|
| 209 |
1. Matunda Primary 2. Malinda S.A Primary 3. Kulisiru Primary 4. Namunyu Primary, 5. Chebukutuni Primary, 6 Lutaso Primary 7. Namawanga Primary |
BUMULA |
MALAKISI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 210 |
Construction of maternity at Bisunu dispensary |
BUMULA |
MALAKISI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 211 |
Dilling and Installation of 01 Borehole at Ndakaru Primary |
BUMULA |
MALAKISI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 212 |
construction of one ECDE Classroom Wamong’oli |
WEBUYE EAST |
MATULO |
Wamang’oli |
|
|
970,000.00 |
905,683.00 |
64,317.00 |
Complete |
|
|
|
| 213 |
Road mantainance – matulo corner road |
WEBUYE EAST |
MATULO |
matulo |
|
|
2,346,158.00 |
2,135,002.98 |
211,155.02 |
Complete |
|
|
|
| 214 |
Periodic Maintenance of matulo – simalabandu – kiwanja ndege -matulo fym road |
WEBUYE EAST |
MATULO |
matulo – simalabandu – kiwanja ndege -matulo fym |
|
|
3,940,230.00 |
2,477,090.28 |
1,463,139.72 |
Complete |
|
|
|
| 215 |
Periodic Maintenance of Minata-Malaha road 4km |
WEBUYE EAST |
MATULO |
Minata-Malaha |
|
|
10,320,114.00 |
8,212,289.00 |
2,107,825.00 |
Complete |
|
|
|
| 216 |
Periodic maintenance of roads in Matulo ward |
WEBUYE EAST |
MATULO |
0 |
|
|
11,381,601.00 |
– |
– |
Complete |
|
|
|
| 217 |
CONSTRUCTION OF MATULO-WAMANG’OLI PIPELINE WATER PROJECT |
WEBUYE EAST |
MATULO |
Matulo |
|
|
2,537,191.00 |
– |
– |
Complete |
|
|
|
| 218 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT WEBUYE DEB AND MATULO FYM PRIMARY SCHOOLS IN MATULO WARD |
WEBUYE EAST |
MATULO |
Webuye DEB,Matulo pri |
|
|
2,786,580.00 |
– |
– |
Complete |
|
|
|
| 219 |
Periodic Maintenance of Matumbai-Mtuta-Main Road-Chibukosi(sudi)-Khabwabi Bridge extension of Matumbai Stretch to the Swamp |
WEBUYE EAST |
MATULO |
Matulo |
|
|
– |
– |
– |
Complete |
|
|
|
| 220 |
periodic Maintenance of simala bandu-ndakuya road 1.7km |
WEBUYE EAST |
MATULO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 221 |
periodic Maintenance of mulati-Flyover -molo road 1.5 |
WEBUYE EAST |
MATULO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 222 |
Bursaries |
MT. ELGON |
ELGON |
Elgon |
|
|
500,000.00 |
500,000.00 |
– |
Complete |
|
|
|
| 223 |
purchase of 22,763 coffee seedlings for farmers |
MT. ELGON |
ELGON |
Elgon |
|
|
455,260.00 |
455,260.00 |
– |
Complete |
|
|
|
| 224 |
Bursaries |
MT. ELGON |
ELGON |
Elgon |
|
|
500,000.00 |
500,000.00 |
– |
Complete |
|
|
|
| 225 |
Rehabilitation of Natembea & Keshan wells |
MT. ELGON |
ELGON |
Natembe & Keshan |
|
|
1,131,005.00 |
1,017,904.00 |
113,101.00 |
Complete |
|
|
|
| 226 |
Sports materials |
MT. ELGON |
ELGON |
Elgon |
|
|
499,500.00 |
499,500.00 |
– |
Complete |
|
|
|
| 227 |
Bursaries |
MT. ELGON |
ELGON |
Elgon |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 228 |
Purchase of coffee seedlings |
MT. ELGON |
ELGON |
Elgon |
|
|
2,500,000.00 |
2,500,000.00 |
– |
Complete |
|
|
|
| 229 |
Mantainance of Joseph Bugaa- Kibundo Rd |
MT. ELGON |
ELGON |
Joseph-Bugaa-Kibundo |
|
|
16,716,876.00 |
9,751,333.00 |
6,965,543.00 |
Complete |
|
|
|
| 230 |
Peridic maintenance of roads in Elgon ward( |
MT. ELGON |
ELGON |
Elgon |
|
|
7,980,336.00 |
– |
– |
Complete |
|
|
|
| 231 |
CONSTRUCTION OF WATER PIPELINE EXTENSION OF NAMORIO |
MT. ELGON |
ELGON |
Elgon |
|
|
5,933,608.80 |
– |
– |
Complete |
|
|
|
| 232 |
Sambocho water project |
MT. ELGON |
ELGON |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 233 |
Construction of Mwetuny Bridge |
MT. ELGON |
ELGON |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 234 |
purchase of 1/2 acre land for kongit Dispensary |
MT. ELGON |
KAPTAMA |
Kongit |
|
|
200,000.00 |
200,000.00 |
– |
Complete |
|
|
|
| 235 |
purchase 1/2 acre land Chemoge dispensary |
MT. ELGON |
KAPTAMA |
Chemoge |
|
|
300,000.00 |
300,000.00 |
– |
Complete |
|
|
|
| 236 |
purchase of 1 acre land for Kaboram Sec. School |
MT. ELGON |
KAPTAMA |
Kaborom |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 237 |
Periodic maintenance of Kaptama- Chepkerer road |
MT. ELGON |
KAPTAMA |
Kaptama- Chepkerer |
|
|
6,943,226.00 |
6,047,903.00 |
895,323.00 |
Complete |
|
|
|
| 238 |
Completion of outpatient department for Kaptama health centre |
MT. ELGON |
KAPTAMA |
kaptama |
|
|
9,741,352.88 |
6,911,966.00 |
2,829,386.88 |
Complete |
|
|
|
| 239 |
erection and completion of chemoge dispensary |
MT. ELGON |
KAPTAMA |
Chemoge |
|
|
3,351,566.00 |
3,034,892.30 |
316,673.70 |
Complete |
|
|
|
| 240 |
erection and completion of kongit dispensary |
MT. ELGON |
KAPTAMA |
Kongit |
|
|
3,350,000.00 |
3,243,724.00 |
106,276.00 |
Complete |
|
|
|
| 241 |
Peridic maintenance of roads in Kaptama ward (Kaptama-kastoi-chelilde road 3.0km, chepkoya-kijana-kipmwiyei road 1.5km, kaptama footbridge) |
MT. ELGON |
KAPTAMA |
0 |
|
|
7,040,100.90 |
– |
7,040,100.90 |
Complete |
|
|
|
| 242 |
CONSTRUCTION OF CHESITO KAPTAMA |
MT. ELGON |
KAPTAMA |
0 |
|
|
5,391,680.00 |
– |
– |
Complete |
|
|
|
| 243 |
CONSTRUCTION OF 01 NO.ECDE CLASSROOM AT CHEPSOIKEL AND KIPTIROKO PRIMARY SCHOOLS |
MT. ELGON |
KAPTAMA |
Chepsokel,kiptiroko |
|
|
3,366,540.00 |
– |
– |
Complete |
|
|
|
| 244 |
Periodic Maintenance of Kaptama- Chesinendet Tank Road |
MT. ELGON |
KAPTAMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 245 |
Periodic Maintenance of Chemoge Market – Primary School Road |
MT. ELGON |
KAPTAMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 246 |
Periodic maintenance of Kapsamii- Kamatira- Road |
MT. ELGON |
KAPTAMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 247 |
Protection of water springs at mihuu |
WEBUYE WEST |
MIHUU |
Mihuu |
|
|
116,614.00 |
116,614.00 |
– |
Complete |
|
|
|
| 248 |
Protection of water springs at mapesa |
WEBUYE WEST |
MIHUU |
Mapesa |
|
|
116,614.00 |
116,614.00 |
– |
0 |
|
|
|
| 249 |
Protection of water springs at wafula |
WEBUYE WEST |
MIHUU |
Wafula |
|
|
116,614.00 |
116,614.00 |
– |
0 |
|
|
|
| 250 |
Protection of water springs at Nabiswa |
WEBUYE WEST |
MIHUU |
Nabiswa |
|
|
116,614.00 |
116,614.00 |
– |
0 |
|
|
|
| 251 |
Protection of water springs at Fwamba |
WEBUYE WEST |
MIHUU |
Fwamba |
|
|
116,614.00 |
116,614.00 |
– |
0 |
|
|
|
| 252 |
1No Bodaboda shed |
WEBUYE WEST |
MIHUU |
Lugulu |
|
|
128,014.00 |
128,014.00 |
– |
Complete |
|
|
|
| 253 |
1 No Bodaboda shed |
WEBUYE WEST |
MIHUU |
Furoyi |
|
|
128,014.00 |
128,014.00 |
– |
0 |
|
|
|
| 254 |
Periodic mantainance of misimo- mabele- mwalimu khainda road |
WEBUYE WEST |
MIHUU |
mabele |
|
|
7,658,552.00 |
5,524,312.00 |
2,134,240.00 |
Complete |
|
|
|
| 255 |
Periodic Mantainance of Njurubani – Ngome road |
WEBUYE WEST |
MIHUU |
Njurubani-Ngome |
|
|
1,995,804.00 |
1,124,707.00 |
871,097.00 |
Complete |
|
|
|
| 256 |
Lease of land for gravel |
WEBUYE WEST |
MIHUU |
Mihuu |
|
|
250,000.00 |
250,000.00 |
– |
Complete |
|
|
|
| 257 |
purchase of 1 acre land for Bakisa youth polytechnic |
WEBUYE WEST |
MIHUU |
Bakisa |
|
|
545,000.00 |
545,000.00 |
– |
Complete |
|
|
|
| 258 |
Periodic Mantainance of Stanley – Ngoya – Fwamba bridge road |
WEBUYE WEST |
MIHUU |
Stanley – Ngoya – Fwamba |
|
|
7,469,704.00 |
6,047,265.00 |
1,422,439.00 |
Complete |
|
|
|
| 259 |
construction of maternity wing at mihuu dispensary |
WEBUYE WEST |
MIHUU |
Mihuu |
|
|
3,373,560.00 |
– |
– |
Complete |
|
|
|
| 260 |
CONSTRUCTION OF MITUKUYU SUBLOCATION WATER SPRINGS PROJECT |
WEBUYE WEST |
MIHUU |
0 |
|
|
3,436,776.00 |
– |
– |
Complete |
|
|
|
| 261 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT FROY LUGULU, PAG PRIMARY AND MURUMBA PRIMARY SCHOOLS IN MIHUU WARD |
WEBUYE WEST |
MIHUU |
Murumba,froy,lugulu PAG |
|
|
4,140,960.00 |
– |
– |
Complete |
|
|
|
| 262 |
Purchase of land for Savana Dispensary |
WEBUYE WEST |
MIHUU |
Savana |
|
|
800,000.00 |
– |
– |
Complete |
|
|
|
| 263 |
construction of 2 NO door pit latrines |
WEBUYE WEST |
MIHUU |
lukusi, lugulu, furoyi and 4 NO. pit latrines |
|
|
– |
– |
– |
Complete |
|
|
|
| 264 |
Toili box-culverts-River Lukusi |
WEBUYE WEST |
MIHUU |
Mihuu |
|
|
– |
– |
– |
Complete |
|
|
|
| 265 |
Periodic maintenance of Sipala-Kangale -Marani-Mulachi-Makona road 4km |
WEBUYE WEST |
MIHUU |
MIHUU |
|
|
– |
– |
– |
Complete |
|
|
|
| 266 |
Construction of kongoli ECDE classroom |
KANDUYI |
BUKEMBE EAST |
kongoli |
|
|
959,498.00 |
959,498.00 |
– |
Complete |
|
|
|
| 267 |
Purchase of 1 acre land for Sango ECDE Centre |
KANDUYI |
BUKEMBE EAST |
kongoli |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 268 |
Construction of Bodaboda sheds at kongoli,Nandolia,Bukembe |
KANDUYI |
BUKEMBE EAST |
kongoli,Nandolia,Bukembe |
|
|
798,486.00 |
733,229.50 |
65,256.50 |
Complete |
|
|
|
| 269 |
Construction of Misanga ECDE classroom |
KANDUYI |
BUKEMBE EAST |
Misanga |
|
|
964,905.40 |
789,634.00 |
175,271.40 |
Complete |
|
|
|
| 270 |
Construction of Bukembe Pri. ECDE classroom |
KANDUYI |
BUKEMBE EAST |
Bukembe Pri. |
|
|
1,049,825.00 |
524,520.00 |
525,305.00 |
Complete |
|
|
|
| 271 |
mantainance of Siata – Walucho road |
KANDUYI |
BUKEMBE EAST |
Siata-Walucho |
|
|
7,119,210.00 |
6,169,192.00 |
950,018.00 |
Complete |
|
|
|
| 272 |
Periodic mantainance of Kongoli mkt-Tembelela road |
KANDUYI |
BUKEMBE EAST |
Kongoli mkt-Tembelela |
|
|
6,575,877.60 |
6,362,543.00 |
213,334.60 |
Complete |
|
|
|
| 273 |
Peridic maintenance of roads in Bukembe East ward |
KANDUYI |
BUKEMBE EAST |
Bukembe east |
|
|
2,654,022.00 |
– |
– |
Complete |
|
|
|
| 274 |
Equipping of maternity ward at Bukembe dispensary |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 275 |
CONSTRUCTION OF NAVAKHOLO BOREHOLE WATER PROJECT |
KANDUYI |
BUKEMBE EAST |
Navakholo |
|
|
3,725,521.00 |
– |
– |
Complete |
|
|
|
| 276 |
CONSTRUCTION OF 2NO MARKET SHEDS, AT BUKEMBE AND NANDOLIA MARKET |
KANDUYI |
BUKEMBE EAST |
Bukembe, Nandolia |
|
|
1,309,060.00 |
– |
– |
Complete |
|
|
|
| 277 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AT INDUSTRIAL AREA, HUTUTU AND SANGO PRIMARY SCHOOL IN BUKEMBE EAST WARD |
KANDUYI |
BUKEMBE EAST |
Hututu,Sango |
|
|
– |
– |
– |
Complete |
|
|
|
| 278 |
Purchase of 1 acre for Natundwe dispensary |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
700,000.00 |
– |
– |
Complete |
|
|
|
| 279 |
Purchase of 1 acre for Sitawa E.C.D.E |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
950,000.00 |
– |
– |
Complete |
|
|
|
| 280 |
Purchase of ¾ of an acre for Namirembe dispensary |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 281 |
Tree planting at Hututu,Bukembe S.A,at Chiefs office,kongoli dispensary,Bukembe and Nandolia market |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
400,000.00 |
– |
– |
Complete |
|
|
|
| 282 |
Proposed completion of 4 door pit latrines |
KANDUYI |
BUKEMBE EAST |
kongoli, nandolia and bukembe markets |
|
|
2,500,000.00 |
– |
– |
Complete |
|
|
|
| 283 |
Box culvert at kombo primary- sango ecde centre a cross river BOKOLI |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 284 |
Periodic maintenance Machinjoni- Proffessor- Sudi market road |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 285 |
Drilling of a Borehole at Misanga markets |
KANDUYI |
BUKEMBE EAST |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 286 |
mantainance of Nakalila- misemwa road |
KIMILILI |
KAMUKUYWA |
marofu |
|
|
2,799,544.00 |
2,095,374.00 |
704,170.00 |
Complete |
|
|
|
| 287 |
Construction of Nakalila-Mukuyuni box culvert |
KIMILILI |
KAMUKUYWA |
0 |
|
|
8,197,024.00 |
2,799,544.00 |
5,397,480.00 |
Complete |
|
|
|
| 288 |
mantainance of mwangale- marofu road |
KIMILILI |
KAMUKUYWA |
marofu |
|
|
3,800,000.00 |
3,253,239.00 |
546,761.00 |
Complete |
|
|
|
| 289 |
Peridic maintenance of roads in Kamukuywa ward(3.6km) |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
6,110,706.00 |
– |
6,110,706.00 |
Complete |
|
|
|
| 290 |
CONSTRUCTION OF CHESAMISI –MUKHUYU PIPELINE AND 9NO. WATER SPRINGS |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
2,496,315.00 |
– |
– |
Complete |
|
|
|
| 291 |
PROPOSED SOLAR POWERED FLOODLIGHTS |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
2,600,000.00 |
– |
– |
Complete |
|
|
|
| 292 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT MATISI, LUBOKHA, CHESAMIS AND SOSIO PRIMARY SCHOOLS IN KAMUKUYWA WARD |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
3,999,950.00 |
– |
– |
Complete |
|
|
|
| 293 |
periodic maintenance of Sokomoko -Matisi road |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
– |
– |
– |
Complete |
|
|
|
| 294 |
Periodic maintenance of Zakayo-Imani road 1km |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
– |
– |
– |
Complete |
|
|
|
| 295 |
Periodic maintenance of Musembe road 1km |
KIMILILI |
KAMUKUYWA |
Kamukuywa |
|
|
– |
– |
– |
Complete |
|
|
|
| 296 |
Construction of Bumula primary-Railway crossing- Mukuyuni Road 5km |
BUMULA |
BUMULA |
Bumula |
|
|
838,745.00 |
838,745.00 |
– |
Complete |
|
|
|
| 297 |
Grading gravelling of Bumula- mukuyuni road |
BUMULA |
BUMULA |
Bumula |
|
|
3,764,200.00 |
2,122,640.00 |
1,641,560.00 |
Complete |
|
|
|
| 298 |
Supply of the buiding materials at Musia ECDE Centre |
BUMULA |
BUMULA |
Musia |
|
|
809,150.00 |
695,098.00 |
114,052.00 |
Complete |
|
|
|
| 299 |
Periodic mantainance of Sikinga Namaika road |
BUMULA |
BUMULA |
Sikinga-Namaika |
|
|
3,928,000.00 |
3,400,923.00 |
527,077.00 |
Complete |
|
|
|
| 300 |
Periodic mantainance of Wekelekha- weighbridge- Siekumulo. road |
BUMULA |
BUMULA |
Wekelekha- weighbridge- Siekumulo |
|
|
5,808,642.00 |
5,196,918.00 |
611,724.00 |
Complete |
|
|
|
| 301 |
School empowerment programme |
BUMULA |
BUMULA |
0 |
|
|
1,000,000.00 |
1,000,000.00 |
– |
Complete |
|
|
|
| 302 |
Purchase of 1 acre land for Lurare ECDE Cetnre |
BUMULA |
BUMULA |
Lurare |
|
|
500,000.00 |
500,000.00 |
– |
Complete |
|
|
|
| 303 |
Construction of 16. no. water springs |
BUMULA |
BUMULA |
0 |
|
|
2,502,144.00 |
2,047,445.00 |
454,699.00 |
Complete |
|
|
|
| 304 |
Peridic maintenance of roads in Bumula ward(Sikinga-Mwenge Rd2.3km) |
BUMULA |
BUMULA |
Bumula |
|
|
6,278,302.80 |
– |
– |
Complete |
|
|
|
| 305 |
constuction of 1 outpatient room at mabusi dispensary |
BUMULA |
BUMULA |
Mabusi |
|
|
5,756,558.00 |
– |
5,756,558.00 |
Complete |
|
|
|
| 306 |
CONSTRUCTION OF BUMULA WATER SPRINGS PROJECT IN BUMULA WARD |
BUMULA |
BUMULA |
0 |
|
|
1,925,000.00 |
– |
1,925,000.00 |
Complete |
|
|
|
| 307 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AT MTUA, LURARE, AND COMPLETION OF MUSIYA PRIMARY SCHOOL IN BUMULA WARD |
BUMULA |
BUMULA |
Mtua,Lurare,Musiya |
|
|
3,443,370.00 |
– |
3,443,370.00 |
Complete |
|
|
|
| 308 |
Grading and gravelling Bumula – Lurare-Tabuti 2km road |
BUMULA |
BUMULA |
Bumula |
|
|
– |
– |
– |
Complete |
|
|
|
| 309 |
Construction of 01 no workshop Masuno VTC |
BUMULA |
BUMULA |
Masuno |
|
|
– |
– |
– |
Complete |
|
|
|
| 310 |
Drilling and equiping of boreholes |
BUMULA |
BUMULA |
Mabusi |
|
|
– |
– |
– |
Complete |
|
|
|
| 311 |
Purchase of 1 acre land for mashinani ECDE Centre |
TONGAREN |
SOYSAMBU |
mashinani |
|
|
800,000.00 |
800,000.00 |
– |
Complete |
|
|
|
| 312 |
protection of water spring |
TONGAREN |
SOYSAMBU |
Sifunji |
|
|
165,800.00 |
165,800.00 |
– |
Complete |
|
|
|
| 313 |
Purchase of 1 acre land for Soysambu S.A ECDE |
TONGAREN |
SOYSAMBU |
Soysambu S.A |
|
|
800,000.00 |
650,000.00 |
150,000.00 |
Complete |
|
|
|
| 314 |
Purchase of 1 acre land for St. pauls Narati ECDE |
TONGAREN |
SOYSAMBU |
Narati |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 315 |
Purchase of 1 acre land for Kewa ECDE Centre |
TONGAREN |
SOYSAMBU |
Kewa |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 316 |
Periodic maintenance of Ambeba- mukosa wembe road |
TONGAREN |
SOYSAMBU |
Ambeba- mukosa wembe |
|
|
7,261,716.00 |
5,867,312.00 |
1,394,404.00 |
Complete |
|
|
|
| 317 |
Mantainance of Namatore – Namunyiri sec road |
TONGAREN |
SOYSAMBU |
Namatore-Namunyiri |
|
|
4,914,630.00 |
3,562,924.00 |
1,351,706.00 |
Complete |
|
|
|
| 318 |
grading and murraming of 2kms road from Narati primary to sasaka bridge. |
TONGAREN |
SOYSAMBU |
Narati primary to sasaka |
|
|
7,503,439.00 |
6,323,972.00 |
1,179,467.00 |
Complete |
|
|
|
| 319 |
Periodic maintenance of Zacharia-Mufunje road |
TONGAREN |
SOYSAMBU |
Zacharia-Mufunje |
|
|
3,990,168.00 |
3,183,721.00 |
806,447.00 |
Complete |
|
|
|
| 320 |
Purchase of 1 acre land for Buyanzi ECDE |
TONGAREN |
SOYSAMBU |
0 |
|
|
800,000.00 |
800,000.00 |
|
Complete |
|
|
|
| 321 |
Periodic mantainance of Namatore Wanjusi road |
TONGAREN |
SOYSAMBU |
0 |
|
|
– |
5,004,240.00 |
– |
Complete |
|
|
|
| 322 |
Construction of Misanga dispensary and pit latrines |
TONGAREN |
SOYSAMBU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 323 |
CONSTRUCTION OF 7NO BODABODA SHEDS, AT MABATI TATU, MISANGA, BRIGADIER, MITOTO, NARATI AND SOYSAMBU MARKET |
TONGAREN |
SOYSAMBU |
Misanga, brigadia |
|
|
1,739,652.00 |
– |
1,739,652.00 |
Complete |
|
|
|
| 324 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT BISHOP WABUKALA AND NAMUNYIRI RCEA IN SOYSAMBU WARD |
TONGAREN |
SOYSAMBU |
bishop Wabukala, Namunyiri |
|
|
2,464,060.00 |
– |
2,464,060.00 |
Complete |
|
|
|
| 325 |
Purchase of 1 acre for Bishop Wabukala E.C.D.E |
TONGAREN |
SOYSAMBU |
0 |
|
|
500,000.00 |
– |
500,000.00 |
Complete |
|
|
|
| 326 |
construction of Makutano health center |
TONGAREN |
SOYSAMBU |
Makutano |
|
|
– |
– |
– |
Complete |
|
|
|
| 327 |
purchase of 3 acre land for makutano Health center |
TONGAREN |
SOYSAMBU |
Makutano |
|
|
– |
– |
– |
Yet to Start |
|
|
|
| 328 |
purchase of 1 acre land for Bishop Wabukala ECDE |
TONGAREN |
SOYSAMBU |
0 |
|
|
– |
– |
– |
Yet to Start |
|
|
|
| 329 |
purchase of 1 acre land for Misanga dispensary |
TONGAREN |
SOYSAMBU |
0 |
|
|
– |
– |
– |
Ongoing |
|
|
|
| 330 |
Protection of 6 water spring Khaoya |
WEBUYE WEST |
BOKOLI |
Nakoli |
|
|
160,733.00 |
160,733.00 |
– |
Complete |
|
|
|
| 331 |
Protection of 6 water spring Nakoli |
WEBUYE WEST |
BOKOLI |
Kakai |
|
|
160,733.00 |
160,733.00 |
– |
0 |
|
|
|
| 332 |
Protection of 6 water spring Kakai |
WEBUYE WEST |
BOKOLI |
Soita |
|
|
160,733.00 |
160,733.00 |
– |
0 |
|
|
|
| 333 |
Protection of 6 water spring Soita |
WEBUYE WEST |
BOKOLI |
Nambacha |
|
|
160,733.00 |
160,733.00 |
– |
0 |
|
|
|
| 334 |
Protection of 6 water spring Nambacha |
WEBUYE WEST |
BOKOLI |
Abel |
|
|
160,733.00 |
160,733.00 |
– |
0 |
|
|
|
| 335 |
Protection of 6 water spring Abel |
WEBUYE WEST |
BOKOLI |
Sinoko |
|
|
160,733.00 |
160,733.00 |
– |
Complete |
|
|
|
| 336 |
Drilling of Temba Temba borehole |
WEBUYE WEST |
BOKOLI |
Bokoli |
|
|
1,695,000.00 |
1,556,478.00 |
138,522.00 |
Complete |
|
|
|
| 337 |
Purchase of land-NAMATONDOI ECDE |
WEBUYE WEST |
BOKOLI |
0 |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 338 |
Periodic mantainance of Ominde Rd |
WEBUYE WEST |
BOKOLI |
0 |
|
|
4,954,824.00 |
3,686,226.00 |
1,268,598.00 |
Complete |
|
|
|
| 339 |
Periodic maintenance of poi poi -Nandasaba road |
WEBUYE WEST |
BOKOLI |
0 |
|
|
11,968,677.00 |
8,136,922.00 |
3,831,755.00 |
Complete |
|
|
|
| 340 |
Peridic maintenance of roads in Bokoli ward(Miendo-Namawanga2.6km,Mukhale-Kaita road2.6km) |
WEBUYE WEST |
BOKOLI |
Bokoli |
|
|
9,174,828.00 |
– |
9,174,828.00 |
Complete |
|
|
|
| 341 |
CONSTRUCTION OF 5NO. SPRINGS AND DRILLING OF 1 BOREHOLE |
WEBUYE WEST |
BOKOLI |
0 |
|
|
2,458,624.00 |
– |
2,458,624.00 |
Complete |
|
|
|
| 342 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AT LUKUKU, BOKOLI R.C AND SAWA PRIMARY SCHOOL IN BOKOLI WARD. |
WEBUYE WEST |
BOKOLI |
Bokoli,Sawa |
|
|
3,515,809.00 |
– |
3,515,809.00 |
Complete |
|
|
|
| 343 |
Purchase of 1 acre for milani dispensary |
WEBUYE WEST |
BOKOLI |
0 |
|
|
700,000.00 |
– |
700,000.00 |
Complete |
|
|
|
| 344 |
Purchase of 1 acre for machakha dispensary |
WEBUYE WEST |
BOKOLI |
0 |
|
|
750,000.00 |
– |
750,000.00 |
Complete |
|
|
|
| 345 |
Construction of ecde classrooms and Mahanga primary, Milani, Namilimo primary and Namatondoi primary |
WEBUYE WEST |
BOKOLI |
Mahanga,Milani,Namilimo |
|
|
– |
– |
– |
Complete |
|
|
|
| 346 |
Drilling and sinking of a borehole and installation of hand pump |
WEBUYE WEST |
BOKOLI |
Milani, Lurare |
|
|
– |
– |
– |
Complete |
|
|
|
| 347 |
Drilling and sinking of a borehole and installation of hand pump |
WEBUYE WEST |
BOKOLI |
Chebini |
|
|
– |
– |
– |
Complete |
|
|
|
| 348 |
purchase of land for Kamasielo dispensary |
KIMILILI |
MAENI |
0 |
|
|
1,000,000.00 |
1,000,000.00 |
– |
complete |
|
|
|
| 349 |
purchase of land for Kamusinde Health Center |
KIMILILI |
MAENI |
0 |
|
|
475,500.00 |
475,500.00 |
– |
Complete |
|
|
|
| 350 |
Construction of Sengeli youth polytechnic |
KIMILILI |
MAENI |
Kikwechi |
|
|
1,102,638.00 |
939,569.00 |
163,069.00 |
Complete |
|
|
|
| 351 |
purchase of land for Kikwechi ECDE Classroom |
KIMILILI |
MAENI |
Kamasielo |
|
|
600,000.00 |
600,000.00 |
– |
Complete |
|
|
|
| 352 |
Periodic Maintenance of Mutolo Junction Khwiroro Mayuli Catholic Church Road |
KIMILILI |
MAENI |
0 |
|
|
8,977,933.00 |
7,480,657.00 |
1,497,276.00 |
Complete |
|
|
|
| 353 |
Periodic mantainance of Kapiri sosio road |
KIMILILI |
MAENI |
0 |
|
|
6,752,081.00 |
6,931,050.20 |
– |
Complete |
|
|
|
| 354 |
Proposed Erection & Completion Works for Kamusinde Community Health Cente |
KIMILILI |
MAENI |
0 |
|
|
5,588,479.00 |
4,395,700.00 |
1,192,779.00 |
Complete |
|
|
|
| 355 |
Proposed Erection & Completion Kamasielo dispansary |
KIMILILI |
MAENI |
0 |
|
|
2,101,280.00 |
1,830,830.00 |
270,450.00 |
Complete |
|
|
|
| 356 |
Purchase of land parcel no. kimilili/sikhendu/2973 for cooperative society |
KIMILILI |
MAENI |
0 |
|
|
850,000.00 |
850,000.00 |
– |
Complete |
|
|
|
| 357 |
Peridic maintenance of roads in Maeni ward(Komolo-Teso Rd1.1km) |
KIMILILI |
MAENI |
Maeni |
|
|
2,665,593.00 |
– |
2,665,593.00 |
Complete |
|
|
|
| 358 |
construction of kamasielo maternity ward with toilets inside |
KIMILILI |
MAENI |
Kamasielo |
|
|
1,405,660.00 |
– |
1,405,660.00 |
Complete |
|
|
|
| 359 |
DRILLING AND SINKING OF MAENI AND KAMASIELO BOREHOLES IN MAENI WARD |
KIMILILI |
MAENI |
Meni |
|
|
3,586,680.00 |
– |
3,586,680.00 |
Complete |
|
|
|
| 360 |
CONSTRUCTION OF 4 NO BODABODA SHEDS, AT KAMASIELO, MAYULI, MUKULIMA JUNCTION, KIBISI,JUNCTION, AND MAENI MARKET |
KIMILILI |
MAENI |
Maeni |
|
|
1,201,064.00 |
– |
1,201,064.00 |
Complete |
|
|
|
| 361 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AT Namboani, MAENI and Kamusinde PRIMARY SCHOOL IN MAENI WARD |
KIMILILI |
MAENI |
Maeni, Kamusinde |
|
|
4,315,340.00 |
– |
– |
Complete |
|
|
|
| 362 |
Dilling and Sinking of Borehole and Pump Installation |
KIMILILI |
MAENI |
Sikhendu |
|
|
– |
– |
– |
Complete |
|
|
|
| 363 |
Grading, Graveling and culvert installation at Kibisi-Kamasielo-Kikwechi road |
KIMILILI |
MAENI |
Maeni |
|
|
– |
– |
– |
Complete |
|
|
|
| 364 |
Periodic maintenace of Yembe Road, Kapiri-Sosio Road,Mukulima Nasusi Road |
KIMILILI |
MAENI |
Maeni |
|
|
– |
– |
– |
Complete |
|
|
|
| 365 |
construction of Wambilianga drift |
KIMILILI |
KIMILILI |
0 |
|
|
350,000.00 |
350,000.00 |
– |
Complete |
|
|
|
| 366 |
construction of Mathias drift |
KIMILILI |
KIMILILI |
0 |
|
|
322,322.00 |
322,322.00 |
– |
Complete |
|
|
|
| 367 |
protection of yasindi water spring |
KIMILILI |
KIMILILI |
0 |
|
|
125,000.00 |
125,000.00 |
– |
Complete |
|
|
|
| 368 |
Trees planting – Bituyu & Lwanda sch |
KIMILILI |
KIMILILI |
kimilili – misikhu high way |
|
|
60,000.00 |
60,000.00 |
– |
Complete |
|
|
|
| 369 |
gravelling of Kambini-main road |
KIMILILI |
KIMILILI |
0 |
|
|
9,291,321.00 |
7,013,537.00 |
2,277,784.00 |
Complete |
|
|
|
| 370 |
Construction of bodaboda sheds at Bokoli junc |
KIMILILI |
KIMILILI |
0 |
|
|
496,944.00 |
404,738.00 |
92,206.00 |
Complete |
|
|
|
| 371 |
Periodic mantainance of Chelekei road |
KIMILILI |
KIMILILI |
0 |
|
|
8,665,061.00 |
7,770,370.00 |
894,691.00 |
Complete |
|
|
|
| 372 |
Periodic mantainance of Passpalm road |
KIMILILI |
KIMILILI |
0 |
|
|
4,238,234.00 |
3,231,630.00 |
1,006,604.00 |
Complete |
|
|
|
| 373 |
Peridic maintenance of roads in Kimilili ward(Bituyu-Lwanda pri Rd3.4km) |
KIMILILI |
KIMILILI |
0 |
|
|
7,583,268.00 |
– |
7,583,268.00 |
Complete |
|
|
|
| 374 |
construction of 1 block kambini dispensary |
KIMILILI |
KIMILILI |
0 |
|
|
2,424,046.20 |
– |
2,424,046.20 |
Complete |
|
|
|
| 375 |
LANDSCAPING AT KATIBA GROUNDS |
KIMILILI |
KIMILILI |
0 |
|
|
934,700.00 |
– |
934,700.00 |
Complete |
|
|
|
| 376 |
THE PROPOSED AND COMPLETION OF 1 N0 CLASSROOM AT KAMULATI, PUNDA AND TMISIKHU S.D.A PRIMARY SCHOOL IN KIMILILI WARD |
KIMILILI |
KIMILILI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 377 |
Purchase of 1 acre for Kambini dispensary |
KIMILILI |
KIMILILI |
0 |
|
|
850,000.00 |
– |
850,000.00 |
Complete |
|
|
|
| 378 |
Periodic Maintenance of Ararat Road |
KIMILILI |
KIMILILI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 379 |
ompletion of Paspalam Road |
KIMILILI |
KIMILILI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 380 |
Periodic Maintenance of Munanda Road-Kimilili Old Market |
KIMILILI |
KIMILILI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 381 |
Construction of Boda Boda Sheds at Matili and Bahai |
KIMILILI |
KIMILILI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 382 |
purchase of 1 acreland – HEALTH CENTRE |
WEBUYE WEST |
MILIMA |
Mukuyuni market |
|
|
800,000.00 |
800,000.00 |
– |
Complete |
|
|
|
| 383 |
Protection of water spring |
WEBUYE WEST |
MILIMA |
Miguu |
|
|
156,150.00 |
156,150.00 |
– |
Complete |
|
|
|
| 384 |
supply of the hospital equipment to Lukhokhwe dispensary |
WEBUYE WEST |
MILIMA |
Lukhokwe |
|
|
386,335.00 |
335,533.00 |
50,802.00 |
Complete |
|
|
|
| 385 |
Periodic maintenance of Maliki- Liambila road 2KMS |
WEBUYE WEST |
MILIMA |
Maliki |
|
|
1,568,418.00 |
1,258,336.00 |
310,082.00 |
Complete |
|
|
|
| 386 |
Grading gravelling of Shandumba – Shivachi Rd |
WEBUYE WEST |
MILIMA |
Milima |
|
|
1,024,452.00 |
720,213.00 |
304,239.00 |
Complete |
|
|
|
| 387 |
Grading and gravelling of Line moja road |
WEBUYE WEST |
MILIMA |
Line moja |
|
|
1,568,418.00 |
1,106,465.00 |
– |
Complete |
|
|
|
| 388 |
Grading gravelling of Nabingenge sitabicha Rd |
WEBUYE WEST |
MILIMA |
Sitabicha |
|
|
1,731,387.00 |
887,989.00 |
843,398.00 |
Complete |
|
|
|
| 389 |
Periodic maintenance of Makunga-Kwena road 2km |
WEBUYE WEST |
MILIMA |
Kwena |
|
|
1,351,875.00 |
1,041,436.00 |
310,439.00 |
Complete |
|
|
|
| 390 |
Grading and gravelling of Namboko road |
WEBUYE WEST |
MILIMA |
Namboko |
|
|
1,179,389.40 |
937,325.00 |
242,064.40 |
Complete |
|
|
|
| 391 |
Laying of water pipeline from maliki sec & installation of Elevated plastic storage tanks at Maliki dispensary. |
WEBUYE WEST |
MILIMA |
Makiki |
|
|
3,080,700.00 |
2,828,932.00 |
251,768.00 |
Complete |
|
|
|
| 392 |
Erection and completion of Mukuyun& Eluya dispensary with 2 door pit latrine |
WEBUYE WEST |
MILIMA |
Eluya,Mukuyuni |
|
|
4,729,946.40 |
– |
4,729,946.40 |
Complete |
|
|
|
| 393 |
INSTALLATION OF SOLAR PUMPING UNIT AT MALIKI AND MAKUNGA BOREHOLES IN MILIMA WARD |
WEBUYE WEST |
MILIMA |
Maliki |
|
|
3,113,714.00 |
– |
3,113,714.00 |
Complete |
|
|
|
| 394 |
PROPOSED SOLAR POWERED FLOODLIGHTS |
WEBUYE WEST |
MILIMA |
Milima |
|
|
– |
– |
– |
complete |
|
|
|
| 395 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT MILIMA, MUKUYUNI AND MALIKI PRIMARY SCHOOLS IN MILIMA WARD |
WEBUYE WEST |
MILIMA |
Milima,Mukuyuni,Maliki |
|
|
3,881,352.00 |
– |
3,881,352.00 |
Complete |
|
|
|
| 396 |
Purchase of 01 Acre land for Auction Ring at Maliki |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 397 |
Construction of Boda Boda Sheds at Mufupi, Kwa Area, Maliki,Luuya,Mukuyu |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 398 |
Grading and gravelling maliki-Rising star road 2km |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 399 |
Construction of ECDE classrooms at Mufupi RC primary |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 400 |
Construction of ECDE classrooms at Riverside primary |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 401 |
Construction of ECDE classrooms at Mukhuyu primary |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 402 |
construction and protection of Bondeni Spring, Kombo Sping, Sitweti Spring, Wekesa Wamocha Spring |
WEBUYE WEST |
MILIMA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 403 |
purchase of land for chekwanda ECDE Centre |
KABUCHAI |
MUKUYUNI |
Chekwanda |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 404 |
Construction of Chekwanda ECDE Classroom |
KABUCHAI |
MUKUYUNI |
Chekwanda |
|
|
1,026,990.00 |
197,849.00 |
829,141.00 |
Complete |
|
|
|
| 405 |
Purchase of Land for Buyanji ECDE |
KABUCHAI |
MUKUYUNI |
Buyanji |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 406 |
Periodic mantainance of kuywa sec- sisenter – river kuywa rd |
KABUCHAI |
MUKUYUNI |
kuywa |
|
|
7,902,268.00 |
6,889,183.00 |
1,013,085.00 |
Complete |
|
|
|
| 407 |
Periodic mantainance of sichei-Biliso chwele river road |
KABUCHAI |
MUKUYUNI |
0 |
|
|
4,893,379.00 |
4,183,539.00 |
709,840.00 |
Complete |
|
|
|
| 408 |
Periodic mantainance of sichei-Biliso chwele river road |
KABUCHAI |
MUKUYUNI |
0 |
|
|
4,893,379.00 |
4,183,539.00 |
709,840.00 |
Complete |
|
|
|
| 409 |
Construction of bodaboda sheds at sichei,chebukaka,Kuywa,Lukhoma and Kimalewa |
KABUCHAI |
MUKUYUNI |
0 |
|
|
1,752,000.00 |
1,521,218.00 |
230,782.00 |
Complete |
|
|
|
| 410 |
Construction of Mukuyuni Nakalila box culvert |
KABUCHAI |
MUKUYUNI |
0 |
|
|
6,313,400.00 |
6,313,400.00 |
– |
Complete |
|
|
|
| 411 |
Digging & equipping 2no. Boreholes at Makhonge & rehabilitation of blue triangle borehole |
KABUCHAI |
MUKUYUNI |
0 |
|
|
2,405,990.00 |
1,968,763.50 |
437,226.50 |
Complete |
|
|
|
| 412 |
Peridic maintenance of roads in Mukuyuni ward(Kuywa jntn-sikulu sec-lukhuna road 3.15km,milembe –buyanji-kapkateny road 2.7km) |
KABUCHAI |
MUKUYUNI |
Mukuyuni |
|
|
8,867,405.40 |
– |
8,867,405.40 |
Complete |
|
|
|
| 413 |
completion of Sikulu health centre |
KABUCHAI |
MUKUYUNI |
Sikulu |
|
|
– |
– |
– |
Complete |
|
|
|
| 414 |
CONSTRUCTION OF MUKUYUNI WATER SPRINGS AND BOREHOLE DRILLING PROJECT |
KABUCHAI |
MUKUYUNI |
0 |
|
|
2,883,237.50 |
– |
2,883,237.50 |
Complete |
|
|
|
| 415 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT ST.CHARLES BUYANJI AND MAKHOMGE PRIMARY SCHOOLS AND RENOVATION OF MUKUYUNI VOCATIONAL TRAINING CENTRE IN MUKUYUNI WARD |
KABUCHAI |
MUKUYUNI |
Makhonge |
|
|
3,745,396.40 |
– |
3,745,396.40 |
Complete |
|
|
|
| 416 |
Sichei Primary School-Chengeni-Samita Primary |
KABUCHAI |
MUKUYUNI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 417 |
Periodic Maintenance of Marimba-Siambi Kibisi Road |
KABUCHAI |
MUKUYUNI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 418 |
Periodic Maintenance of Teremi Primary School-Mukuyuni Cattle Dip |
KABUCHAI |
MUKUYUNI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 419 |
Protection of 1No water spring at Marobo |
KABUCHAI |
MUKUYUNI |
0 |
|
|
– |
– |
– |
0 |
|
|
|
| 420 |
Protection of 1No water spring at Isaka |
KABUCHAI |
BWAKE/LUUYA |
Marobo |
|
|
142,810.00 |
128,529.00 |
14,281.00 |
Complete |
|
|
|
| 421 |
Protection of 1No water spring at Maafu |
KABUCHAI |
BWAKE/LUUYA |
Isaka |
|
|
141,070.00 |
126,963.00 |
14,107.00 |
Complete |
|
|
|
| 422 |
Protection of 1No water spring at Wefwafwa |
KABUCHAI |
BWAKE/LUUYA |
Maafu |
|
|
141,890.00 |
127,701.00 |
14,189.00 |
Complete |
|
|
|
| 423 |
Protection of 1No water spring at Marofu |
KABUCHAI |
BWAKE/LUUYA |
Wefwafwa |
|
|
141,640.00 |
127,476.00 |
14,164.00 |
Complete |
|
|
|
| 424 |
Protection of 1No water spring at Sarai |
KABUCHAI |
BWAKE/LUUYA |
Marofu |
|
|
141,070.00 |
126,963.00 |
14,107.00 |
Complete |
|
|
|
| 425 |
Protection of 1No water spring at Sarai |
KABUCHAI |
BWAKE/LUUYA |
Sarai |
|
|
144,740.00 |
130,266.00 |
14,474.00 |
Complete |
|
|
|
| 426 |
Protection of 1No water spring at Mechumo |
KABUCHAI |
BWAKE/LUUYA |
Mechumo |
|
|
142,610.00 |
128,349.00 |
14,261.00 |
Complete |
|
|
|
| 427 |
2 ACRES OF LAND- MATUNDA ECDE |
KABUCHAI |
BWAKE/LUUYA |
MATUNDA |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 428 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Khachonge |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 429 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Lurende |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 430 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Mabanga |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 431 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Nalondo |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 432 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Luuya |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 433 |
Construction of 1no. Bodaboda shed |
KABUCHAI |
BWAKE/LUUYA |
Chekulo |
|
|
249,284.00 |
249,152.00 |
132.00 |
Complete |
|
|
|
| 434 |
Grading and gravelling of sichei- nabwi-misri and namilama |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
8,609,491.00 |
7,535,884.00 |
1,073,607.00 |
Complete |
|
|
|
| 435 |
2 ACRES OF LAND- MATUNDA ECDE |
KABUCHAI |
BWAKE/LUUYA |
MATUNDA |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 436 |
Construction of Kibochi-Nasaka foorbridge |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
4,407,942.00 |
– |
4,407,942.00 |
Complete |
|
|
|
| 437 |
DRILLING OF KHATIRI PRIMARY SCHOOL BOREHOLE |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
2,045,080.00 |
– |
2,045,080.00 |
Complete |
|
|
|
| 438 |
DRILLING OF MIKAYU SECONDARY SCHOOL BOREHOLE |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
1,903,759.00 |
– |
1,903,759.00 |
Complete |
|
|
|
| 439 |
DRILLLING AND SINKING OF KIBOCHI POLYTECHNIC BOREHOLE AND CONTRUCTION AND PROTECTION OF 2NO. WATER SPRINGS |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
3,224,880.00 |
– |
3,224,880.00 |
Complete |
|
|
|
| 440 |
CONSTRUCTION OF 01 NO. ECDE CLASSROOM AT MATUNDA, CHEKULO, MISIRI RC, NAMIKELO, SANGO AND NANGUBO PRIMARY SCHOOLS. |
KABUCHAI |
BWAKE/LUUYA |
Matunda,Chekulo,Namikelo |
|
|
8,048,219.00 |
– |
8,048,219.00 |
Complete |
|
|
|
| 441 |
Purchase of 0.218 H and Buildings |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
520,000.00 |
– |
520,000.00 |
Complete |
|
|
|
| 442 |
Grading and gravelling of Marobo, luuya girls to chekulo market |
KABUCHAI |
BWAKE/LUUYA |
0 |
|
|
– |
– |
– |
0 |
|
|
|
| 443 |
Construction of 1 ECDE Classroom at Marobo |
KABUCHAI |
BWAKE/LUUYA |
Marobo |
|
|
– |
– |
– |
Complete |
|
|
|
| 444 |
Construction of 1 ECDE Classroom at Chekulo |
KABUCHAI |
BWAKE/LUUYA |
Chekulo |
|
|
– |
– |
– |
Complete |
|
|
|
| 445 |
Construction of 1 ECDE Classroom at Nangili |
KABUCHAI |
BWAKE/LUUYA |
Nangili |
|
|
– |
– |
– |
Complete |
|
|
|
| 446 |
construction and protection of 1NO water spring |
KABUCHAI |
BWAKE/LUUYA |
webala |
|
|
– |
– |
– |
Complete |
|
|
|
| 447 |
construction of shallow well (4NO) |
BUMULA |
SOUTH BUKUSU |
GIVE LOCATION |
|
|
712,115.00 |
500,000.00 |
212,115.00 |
Complete |
|
|
|
| 448 |
Construction and protection of Sifuniame water spring |
BUMULA |
SOUTH BUKUSU |
Sifuniame |
|
|
125,990.00 |
125,990.00 |
– |
Complete |
|
|
|
| 449 |
Construction of BodaBoda shades at Lunakwe |
BUMULA |
SOUTH BUKUSU |
LUNAKWE |
|
|
220,500.00 |
181,085.00 |
39,415.00 |
Complete |
|
|
|
| 450 |
Construction of Bodaboda shades at Mateka market |
BUMULA |
SOUTH BUKUSU |
MATEKA |
|
|
220,500.00 |
203,134.00 |
17,366.00 |
Complete |
|
|
|
| 451 |
mantainance of Nandigwa-lunakwe-lumboka – mulukoma road |
BUMULA |
SOUTH BUKUSU |
lumboka |
|
|
12,721,720.00 |
9,282,576.54 |
3,439,143.46 |
Complete |
|
|
|
| 452 |
purchase of 4.2 acre of land for kibabii university |
BUMULA |
SOUTH BUKUSU |
lunakwe |
|
|
3,100,000.00 |
3,100,000.00 |
– |
Complete |
|
|
|
| 453 |
Rehabilitation of 2no. Shallow |
BUMULA |
SOUTH BUKUSU |
0 |
|
|
148,024.00 |
148,024.00 |
– |
Complete |
|
|
|
| 454 |
Supplly install,test & commission of 14no. Solar light |
BUMULA |
SOUTH BUKUSU |
0 |
|
|
4,156,629.75 |
3,871,628.00 |
285,001.75 |
Complete |
|
|
|
| 455 |
Peridic maintenance of roads in South Bukusu ward(Muanda-tulumba road2.8km) |
BUMULA |
SOUTH BUKUSU |
South Bukusu |
|
|
4,406,967.60 |
– |
4,406,967.60 |
Complete |
|
|
|
| 456 |
Construction of maternity wing and fencing of Lunakwe dispensary |
BUMULA |
SOUTH BUKUSU |
Lunakwe |
|
|
2,088,310.00 |
– |
2,088,310.00 |
Complete |
|
|
|
| 457 |
DRILLING OF 2NO. BOREHOLES AT SERETI AND MUANDA |
BUMULA |
SOUTH BUKUSU |
Sereti/ Muanda |
|
|
4,113,480.00 |
– |
4,113,480.00 |
Complete |
|
|
|
| 458 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT NAKHOLO, ECDE CLASSROOM AND TOILET AT NANDINGWA, ECDE CLASSROOM AND TOILET AT TABUTI PRIMARY AND ECDE CLASSROOM AND TOILET AT TULUMBA PRIMARY IN SOUTH BUKUSU WARD |
BUMULA |
SOUTH BUKUSU |
Nakholo,Tabuti |
|
|
4,664,400.00 |
– |
4,664,400.00 |
Complete |
|
|
|
| 459 |
Purchase of 1 acre for Sereti junction E.C.D.E |
BUMULA |
SOUTH BUKUSU |
0 |
|
|
650,000.00 |
650,000.00 |
– |
Complete |
|
|
|
| 460 |
Purchase of ½ an acre for Kimatuni R.C E.C.D.E |
BUMULA |
SOUTH BUKUSU |
0 |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 461 |
Purchase of 1 acre for Sikata E.C.D.E |
BUMULA |
SOUTH BUKUSU |
0 |
|
|
900,000.00 |
– |
– |
NO documents |
|
|
|
| 462 |
rading and gravelling of 2.5 km road at Tulumba -Sichekereni- Road |
BUMULA |
SOUTH BUKUSU |
South Bukusu |
|
|
– |
– |
– |
Complete |
|
|
|
| 463 |
Grading and gravelling of 4.1km road at Tulumba -Tabuti-Mateka Road |
BUMULA |
SOUTH BUKUSU |
South Bukusu |
|
|
– |
– |
– |
Complete |
|
|
|
| 464 |
Installation of solar security lights |
KANDUYI |
TOWNSHIP |
Chebkube market |
|
|
838,106.30 |
838,106.30 |
– |
Complete |
|
|
|
| 465 |
Mantainance of wings Nambaya Rd |
KANDUYI |
TOWNSHIP |
0 |
|
|
4,139,344.00 |
1,865,147.00 |
2,274,197.00 |
Complete |
|
|
|
| 466 |
Construction of 1no. Water kiosk and installation of tank |
KANDUYI |
TOWNSHIP |
Mandizini |
|
|
1,158,215.00 |
1,011,393.70 |
146,821.30 |
Complete |
|
|
|
| 467 |
Construction of 1no. Water kiosk and installation of tank |
KANDUYI |
TOWNSHIP |
Six estate |
|
|
1,158,215.00 |
1,011,393.70 |
146,821.30 |
Complete |
|
|
|
| 468 |
Construction of 1no. Water kiosk and installation of tank |
KANDUYI |
TOWNSHIP |
Oldrex |
|
|
1,158,215.00 |
1,358,857.70 |
(200,642.70) |
Complete |
|
|
|
| 469 |
Periodic Mantainance of DEB -Bishop macheusi Rd |
KANDUYI |
TOWNSHIP |
Deb |
|
|
5,239,836.00 |
4,113,461.00 |
1,126,375.00 |
Complete |
|
|
|
| 470 |
School empowerment programme |
KANDUYI |
TOWNSHIP |
0 |
|
|
1,000,000.00 |
1,000,000.00 |
– |
Complete |
|
|
|
| 471 |
Periodic maintenance of DEB-Sinoko Primary-Railways Bridge Road. |
KANDUYI |
TOWNSHIP |
Deb |
|
|
3,936,576.00 |
– |
3,936,576.00 |
Complete |
|
|
|
| 472 |
Peridic maintenance of roads in Township ward(Denis Road0.5km,Sinoko-Mulaa0.9km,Lady Irene-Mufutu0.7km) |
KANDUYI |
TOWNSHIP |
township |
|
|
7,036,629.60 |
– |
7,036,629.60 |
Complete |
|
|
|
| 473 |
CONSTRUCTION OF TOWNSHIP SEWER LINE |
KANDUYI |
TOWNSHIP |
0 |
|
|
4,863,200.00 |
– |
4,863,200.00 |
Complete |
|
|
|
| 474 |
PROPOSED SUPPLY AND INSTALLATION OF SOLARPOWERED HIGHMAST FLOODLIGHTS AT CHEPKUBE ,MARKET |
KANDUYI |
TOWNSHIP |
Chepkubee |
|
|
`2032000 |
– |
`2,032,000 |
Complete |
|
|
|
| 475 |
Purchase of 1 acre for Construction of water project |
KANDUYI |
TOWNSHIP |
Kanduyi |
|
|
– |
– |
– |
Complete |
|
|
|
| 476 |
periodic Maintenance of Elegant road |
KANDUYI |
TOWNSHIP |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 477 |
Consstruction of sewer line a long si estate- syende road- mfutu |
KANDUYI |
TOWNSHIP |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 478 |
Construction of Bodaqboda sheds |
KANDUYI |
BUKEMBE WEST |
Ndengelwa |
|
|
181,299.00 |
163,169.10 |
18,129.90 |
Complete |
|
|
|
| 479 |
Construction of Mabanga boboda shade |
KANDUYI |
BUKEMBE WEST |
Mabanga |
|
|
181,299.00 |
163,169.10 |
18,129.90 |
Complete |
|
|
|
| 480 |
Construction of Namirembe boboda shade |
KANDUYI |
BUKEMBE WEST |
Namirembe |
|
|
181,299.00 |
163,169.10 |
18,129.90 |
Complete |
|
|
|
| 481 |
Construction of Ekitale boboda shade |
KANDUYI |
BUKEMBE WEST |
Ekitale |
|
|
181,299.00 |
163,169.10 |
18,129.90 |
Complete |
|
|
|
| 482 |
protection of Mukonyi Water spring |
KANDUYI |
BUKEMBE WEST |
Mukonyi |
|
|
137,400.00 |
119,538.00 |
17,862.00 |
Complete |
|
|
|
| 483 |
Renovation of Lutaso cattle dip |
KANDUYI |
BUKEMBE WEST |
Lutaso |
|
|
66,500.00 |
54,610.00 |
11,890.00 |
Complete |
|
|
|
| 484 |
Construction of Kisuluni culvert |
KANDUYI |
BUKEMBE WEST |
kisuluni |
|
|
2,843,160.00 |
2,208,473.00 |
634,687.00 |
Complete |
|
|
|
| 485 |
Grading, gravelling and murramingat Ndengelwa – Chemche – Khaoya -mashambani road ( 3km) |
KANDUYI |
BUKEMBE WEST |
Bukembe |
|
|
7,688,016.00 |
6,456,710.00 |
1,231,306.00 |
Complete |
|
|
|
| 486 |
Grading, gravelling ,murraming and construction of culverts at Ndengelwa Chwele river road ( 2km) |
KANDUYI |
BUKEMBE WEST |
Bukembe |
|
|
11,207,516.00 |
9,810,476.00 |
1,397,040.00 |
Complete |
|
|
|
| 487 |
purchase of land for Namirembe dispensary |
KANDUYI |
BUKEMBE WEST |
Namirembe |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 488 |
Completion of Ndengelwa dispensary |
KANDUYI |
BUKEMBE WEST |
Ndengeelwa |
|
|
1,344,086.20 |
– |
– |
Complete |
|
|
|
| 489 |
CHEMCHE WATER PROJECT |
KANDUYI |
BUKEMBE WEST |
Bukembe |
|
|
6,330,684.00 |
– |
6,330,684.00 |
Complete |
|
|
|
| 490 |
CONSTRUCTION OF 3 NO BODABODA SHEDS, AT MUYAYI, KHAOYA AND LUTACHO SICHEKERENI. |
KANDUYI |
BUKEMBE WEST |
Muyayi,Khaoya |
|
|
784,942.00 |
– |
784,942.00 |
Complete |
|
|
|
| 491 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT KHAOYA, NAMIREMBE AND MUYAYI PRIMARY SCHOOL IN BUKEMBE WEST WARD |
KANDUYI |
BUKEMBE WEST |
Khaoya,Muyayi,Namirembe |
|
|
3,434,230.00 |
– |
3,434,230.00 |
Complete |
|
|
|
| 492 |
Extension of NZOWASCO Line – 1. Makotelo to Namirembe (New road)- 2. Mabanga market-Namirembe (old road)- 3. Ndengelwa Market- Lutaso village(sichekereni) |
KANDUYI |
BUKEMBE WEST |
Bukembe west |
|
|
– |
– |
– |
Complete |
|
|
|
| 493 |
Construction of 1 Classroom at Namirembe VTC |
KANDUYI |
BUKEMBE WEST |
Namirembe |
|
|
– |
– |
– |
Complete |
|
|
|
| 494 |
construction of 2 classrooms at Muyayi polytechnic |
KANDUYI |
BUKEMBE WEST |
Muyayi, |
|
|
– |
– |
– |
Complete |
|
|
|
| 495 |
planting of trees |
KANDUYI |
BUKEMBE WEST |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 496 |
Construction of Namirembe dispensary |
KANDUYI |
BUKEMBE WEST |
Namirembe |
|
|
– |
– |
– |
Complete |
|
|
|
| 497 |
Construction of Eco-San pit latrines at Ekitale market |
KANDUYI |
BUKEMBE WEST |
Ekitale |
|
|
– |
– |
– |
Complete |
|
|
|
| 498 |
Construction of Eco-San pit latrines at Ndengelwa market |
KANDUYI |
BUKEMBE WEST |
Ndengelwa |
|
|
– |
– |
– |
Complete |
|
|
|
| 499 |
Grading of Sacho pri- daraja mungu -Kamumeru |
MT. ELGON |
KAPKATENY |
Kamumeru |
|
|
957,000.00 |
957,000.00 |
– |
Complete |
|
|
|
| 500 |
Extension of Grading of Sacho pri- daraja mungu -Kamumeru |
MT. ELGON |
KAPKATENY |
Kamumeru |
|
|
2,500,000.00 |
1,883,095.50 |
616,904.50 |
Complete |
|
|
|
| 501 |
Periodic Mantainance of Shiundu – Chelebei market Rd |
MT. ELGON |
KAPKATENY |
0 |
|
|
12,920,776.00 |
10,956,028.00 |
1,964,748.00 |
Complete |
|
|
|
| 502 |
Periodic maintenance of Randa kapsirongo road |
MT. ELGON |
KAPKATENY |
0 |
|
|
1,845,096.00 |
1,370,956.00 |
474,140.00 |
Complete |
|
|
|
| 503 |
Erection and completion of out patient unit at kapkaten dispensary |
MT. ELGON |
KAPKATENY |
0 |
|
|
3,230,803.00 |
2,643,687.00 |
587,116.00 |
Complete |
|
|
|
| 504 |
Peridic maintenance of roads in Kapkatenyi ward(Chebich-cheptakat-toyondet road1.4km) |
MT. ELGON |
KAPKATENY |
0 |
|
|
7,055,143.00 |
– |
7,055,143.00 |
Complete |
|
|
|
| 505 |
CONSTRUCTION OF MATERNITY WING AT KAMUNERU DISPENSARY |
MT. ELGON |
KAPKATENY |
Kamuneru |
|
|
1,411,640.00 |
– |
1,411,640.00 |
Complete |
|
|
|
| 506 |
CONSTRUCTION OF WATER PIPES FROM KAMNERU-SACHO COMMUNITY WATER PROJECTS AND INSTALLTION OF WATER TANK |
MT. ELGON |
KAPKATENY |
Kamuneru- sacho |
|
|
7,243,748.00 |
– |
7,243,748.00 |
Complete |
|
|
|
| 507 |
PROPOSED AND COMPLETION OF 1 N0 CLASSROOM AT KAMUNERU PRIMARY SCHOOL IN KAPKATENY WARD |
MT. ELGON |
KAPKATENY |
Kamumeru |
|
|
1,673,340.00 |
– |
1,673,340.00 |
Complete |
|
|
|
| 508 |
Construction of Kipsabuk Dispensary |
MT. ELGON |
KAPKATENY |
kipsabuk |
|
|
– |
– |
– |
Complete |
|
|
|
| 509 |
Construction of Kapsambu Dispensary |
MT. ELGON |
KAPKATENY |
Kaptanai dispensary |
|
|
– |
– |
– |
Complete |
|
|
|
| 510 |
Construction of Chemositet ECDE |
MT. ELGON |
KAPKATENY |
Chemositet |
|
|
– |
– |
– |
Complete |
|
|
|
| 511 |
Protection of 1No. water spring at binyenya |
TONGAREN |
TONGAREN |
Binyenya |
|
|
160,840.00 |
160,840.00 |
– |
Complete |
|
|
|
| 512 |
Protection of 1No. water spring at Bunambo |
TONGAREN |
TONGAREN |
Bunambo |
|
|
160,840.00 |
160,840.00 |
– |
Complete |
|
|
|
| 513 |
Protection of 1No. water spring at Kakamwe |
TONGAREN |
TONGAREN |
Kakamwe |
|
|
160,840.00 |
160,840.00 |
– |
Complete |
|
|
|
| 514 |
Protection of 1No. water spring at Makololwe |
TONGAREN |
TONGAREN |
Makololwe |
|
|
160,840.00 |
160,840.00 |
– |
Complete |
|
|
|
| 515 |
Protection of 1No. water spring at Makhonge |
TONGAREN |
TONGAREN |
Makhonge |
|
|
160,840.00 |
160,840.00 |
– |
Complete |
|
|
|
| 516 |
Drilling of borehole |
TONGAREN |
TONGAREN |
Binyenya |
|
|
1,751,825.00 |
1,608,750.44 |
143,074.56 |
Complete |
|
|
|
| 517 |
Construction of ECDE C/room at Bituyu & Bunambo |
TONGAREN |
TONGAREN |
Bituyu/Bunambo |
|
|
2,213,291.00 |
1,809,943.00 |
403,348.00 |
Complete |
|
|
|
| 518 |
Mantainance of Kakamwe – Namunyiri road |
TONGAREN |
TONGAREN |
Kakamwe |
|
|
7,733,082.00 |
6,187,628.00 |
1,545,454.00 |
Complete |
|
|
|
| 519 |
Purchase of land for MILELE ECDE |
TONGAREN |
TONGAREN |
0 |
|
|
1,200,000.00 |
1,200,000.00 |
– |
Complete |
|
|
|
| 520 |
Construction of 2 ECDE C/rooms at Mufunje & Mbirira pri. |
TONGAREN |
TONGAREN |
0 |
|
|
2,306,091.60 |
1,884,626.00 |
421,465.60 |
Complete |
|
|
|
| 521 |
Construction of 900mm diameter culvert on r. mabusi |
TONGAREN |
TONGAREN |
0 |
|
|
3,277,658.00 |
2,645,537.00 |
632,121.00 |
Complete |
|
|
|
| 522 |
Peridic maintenance of roads in Tongaren ward(Lukhuna friends –bunambo road 2.8km,Milimani – binyenya road 0.5km) |
TONGAREN |
TONGAREN |
0 |
|
|
8,386,295.40 |
– |
8,386,295.40 |
Complete |
|
|
|
| 523 |
DRILLING AND CONSTRUCTION OF MILIMANI BOREHOLE AND 3NO.SPRINGS IN TONGAREN WARD |
TONGAREN |
TONGAREN |
0 |
|
|
2,988,450.00 |
– |
2,988,450.00 |
Complete |
|
|
|
| 524 |
THE PROPOSED ERECTION AND COMPLETION OF 1 N0 CLASSROOM AND PIT LATRINE AT MAKOLOLWA, MABUSI, MILIMA YOUTH POLYTECHNIC IN TONGAREEN WARD |
TONGAREN |
TONGAREN |
Mabusi,Milima,Makololwa |
|
|
5,891,900.00 |
– |
5,891,900.00 |
Complete |
|
|
|
| 525 |
Purchase of 1 acre for Namakhele E.C.D.E |
TONGAREN |
TONGAREN |
Namakhele |
|
|
850,000.00 |
– |
850,000.00 |
Complete |
|
|
|
| 526 |
Construction of Njiwa bridge |
TONGAREN |
TONGAREN |
Tongaren |
|
|
– |
– |
– |
Complete |
|
|
|
| 527 |
LAND (0.5.acre)- ECDE classroom |
WEBUYE WEST |
MARAKA |
Maraka |
|
|
260,000.00 |
260,000.00 |
– |
Complete |
|
|
|
| 528 |
Construction of 1 No. water kiosk Lukhoba |
WEBUYE WEST |
MARAKA |
Lukhoba |
|
|
203,155.00 |
182,849.00 |
20,306.00 |
Complete |
|
|
|
| 529 |
Construction of 1 No. water kiosk Nangili |
WEBUYE WEST |
MARAKA |
Nangili |
|
|
203,155.00 |
182,849.00 |
20,306.00 |
Complete |
|
|
|
| 530 |
Construction of 1 No. water kiosk Nangota |
WEBUYE WEST |
MARAKA |
Nangota |
|
|
203,133.00 |
– |
203,133.00 |
Complete |
|
|
|
| 531 |
Construction of 900mm diameter box culvert at r. Lufwindiri |
WEBUYE WEST |
MARAKA |
R. Lufwindiri |
|
|
4,219,737.00 |
3,456,359.00 |
763,378.00 |
Complete |
|
|
|
| 532 |
Construction of National box culverts |
WEBUYE WEST |
MARAKA |
0 |
|
|
8,270,220.00 |
6,968,311.00 |
1,301,909.00 |
Complete |
|
|
|
| 533 |
Construction of Kakimanyi- Wananchi- Nasikio culverts |
WEBUYE WEST |
MARAKA |
0 |
|
|
865,742.00 |
606,793.00 |
258,949.00 |
Complete |
|
|
|
| 534 |
Construction of Wanasikoko box culverts |
WEBUYE WEST |
MARAKA |
0 |
|
|
– |
7,088,760.00 |
– |
Complete |
|
|
|
| 535 |
Construction of maternity wing at Lurare health centre |
WEBUYE WEST |
MARAKA |
Lurare |
|
|
2,243,520.00 |
– |
2,243,520.00 |
Complete |
|
|
|
| 536 |
DRILLING OF MUCHI YOUTH POLYTECHNIC AND NANGOTO BOREHOLES |
WEBUYE WEST |
MARAKA |
Muchi |
|
|
3,962,560.00 |
– |
3,962,560.00 |
Complete |
|
|
|
| 537 |
completion of Lukhoba Dispensary |
WEBUYE WEST |
MARAKA |
Lukhoba |
|
|
– |
– |
– |
0 |
|
|
|
| 538 |
Construction of 04 Solar High Flat Mast Lights at Sango Market, Main Bus Park, Upper Hill Estate, Catholic/Wananchi Market, Mukhuyu(mwalimu Estate) |
WEBUYE WEST |
MARAKA |
Sango,Main bus park |
|
|
– |
– |
– |
Complete |
|
|
|
| 539 |
Purchase of Land for Catholic Market |
WEBUYE WEST |
MARAKA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 540 |
construction of Public Toilets at Sango,Nzoia RC ecde,Webuye main market,Catholic market,Mukhuyu ecde,P.A.G ecde Centre,nambuya, |
WEBUYE WEST |
MARAKA |
Sango,nzoia,P.A.G |
|
|
– |
– |
– |
Complete |
|
|
|
| 541 |
grading and gravelling of Kitabisi-Malakisi Road and raising of calverts |
BUMULA |
KIMAETI |
0 |
|
|
957,000.00 |
957,000.00 |
– |
Complete |
|
|
|
| 542 |
Periodic mantainance of Nambuchi- Nakalira- Kitabisi – Sango road |
BUMULA |
KIMAETI |
0 |
|
|
19,524,076.00 |
12,066,155.00 |
7,457,921.00 |
Complete |
|
|
|
| 543 |
Peridic maintenance of roads in Kimaeti ward(Kimwanga-Tabala2.8km,Miyanga-Apokori2.5km) |
BUMULA |
KIMAETI |
0 |
|
|
4,086,877.00 |
– |
4,086,877.00 |
Complete |
|
|
|
| 544 |
completion of maternity wing at Kimaeti Dispensary and construction of myanga dispensary |
BUMULA |
KIMAETI |
Kimaeti,Myanga |
|
|
4,593,250.00 |
– |
4,593,250.00 |
Complete |
|
|
|
| 545 |
ST. JUDE NAPARA GIRLS WATER PROJECT |
BUMULA |
KIMAETI |
0 |
|
|
2,000,000.00 |
– |
2,000,000.00 |
Complete |
|
|
|
| 546 |
CONSTRUCTION OF 4 NO BODABODA SHEDS, 2 AT KIMAETI, 1 IN MYANGA, 1 IN BITOBO |
BUMULA |
KIMAETI |
0 |
|
|
960,480.00 |
– |
960,480.00 |
Complete |
|
|
|
| 547 |
THE PROPOSED AND COMPLETION OF 1 N0 CLASSROOM AT MASIELO AND TULUKUYI PRIMARY SCHOOL IN KIMAETI WARD |
BUMULA |
KIMAETI |
0 |
|
|
2,373,810.00 |
– |
2,373,810.00 |
Complete |
|
|
|
| 548 |
grading gravelling of syombe- tulikuyu 3km |
BUMULA |
KIMAETI |
Kimaeti |
|
|
– |
– |
– |
Complete |
|
|
|
| 549 |
Grading and gravelling of Lelekwe-syombe-kimaeti secondary school |
BUMULA |
KIMAETI |
Kimaeti |
|
|
– |
– |
– |
Complete |
|
|
|
| 550 |
Construction of ECDE classrooms at Napara,Silila,Bukirimo |
BUMULA |
KIMAETI |
Silila,Bukurimo |
|
|
– |
– |
– |
Complete |
|
|
|
| 551 |
Construction of 1 No bodaboda shed at Makhanga |
TONGAREN |
NAITIRI/KABUYEFWE |
Makhanga |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 552 |
Construction of 1 No bodaboda shed at Lungai |
TONGAREN |
NAITIRI/KABUYEFWE |
Lungai |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 553 |
Construction of 1 No bodaboda shed at Nasianda |
TONGAREN |
NAITIRI/KABUYEFWE |
Nasianda |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 554 |
Construction of 1 No bodaboda shed at Mitua |
TONGAREN |
NAITIRI/KABUYEFWE |
Mitua |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 555 |
Construction of 1 No bodaboda shed at Pwani |
TONGAREN |
NAITIRI/KABUYEFWE |
Pwani |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 556 |
Construction of 1 No bodaboda shed at Naitiri |
TONGAREN |
NAITIRI/KABUYEFWE |
Naitiri |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 557 |
Construction of 1 No bodaboda shed at Naitiri Junction |
TONGAREN |
NAITIRI/KABUYEFWE |
Naitiri junction |
|
|
93,377.00 |
81,238.00 |
12,139.00 |
Complete |
|
|
|
| 558 |
Construction of 1 No bodaboda shed at Milembe market |
TONGAREN |
NAITIRI/KABUYEFWE |
Milembe mkt |
|
|
172,500.00 |
150,375.00 |
22,125.00 |
Complete |
|
|
|
| 559 |
Construction of 1 No bodaboda shed at Wabukhonyi |
TONGAREN |
NAITIRI/KABUYEFWE |
Wabukhonyi |
|
|
172,500.00 |
150,375.00 |
22,125.00 |
0 |
|
|
|
| 560 |
Construction of one drift at river Wakwabubi |
TONGAREN |
NAITIRI/KABUYEFWE |
wakwabubi |
|
|
2,187,064.00 |
1,983,543.00 |
203,521.00 |
Complete |
|
|
|
| 561 |
Installation of Tenya 3 no. culverts |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
1,633,338.00 |
1,133,109.00 |
500,229.00 |
Complete |
|
|
|
| 562 |
Periodic Maintenance of wabusia-wangusi road |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
7,188,636.00 |
5,760,352.00 |
1,428,284.00 |
Complete |
|
|
|
| 563 |
Purchase of land for Sango pri. |
TONGAREN |
NAITIRI/KABUYEFWE |
Sango |
|
|
800,000.00 |
800,000.00 |
– |
Complete |
|
|
|
| 564 |
Construction of 1 No bodaboda shed at Nyange |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
199,500.00 |
163,218.00 |
36,282.00 |
Complete |
|
|
|
| 565 |
Construction of 1 No bodaboda shed at Sokomoko |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
199,500.00 |
163,218.00 |
36,282.00 |
Complete |
|
|
|
| 566 |
Construction of 1 No bodaboda shed at Sirakaru |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
199,500.00 |
163,218.00 |
36,282.00 |
Complete |
|
|
|
| 567 |
Periodic Maintenance of Pwani-Yabuna -Sirakaru Road |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
6,664,896.00 |
6,057,431.00 |
607,465.00 |
Complete |
|
|
|
| 568 |
Peridic maintenance of roads in Naitiri/Kabuyefwe ward(Naitiri jnctn-sango-kiminini road2.7km,Sango-mukuusi road1.8km,construction of three lines of culverts at wamanga.) |
TONGAREN |
NAITIRI/KABUYEFWE |
naitiri |
|
|
8,201,037.60 |
– |
8,201,037.60 |
Complete |
|
|
|
| 569 |
Sirakaru Dispensary |
TONGAREN |
NAITIRI/KABUYEFWE |
Sirakaru |
|
|
– |
– |
– |
Complete |
|
|
|
| 570 |
DRILLING AND EQUIPPING OF 2NO. BOREHOLES AND 2NO.SPRING IN NAITIRI WARD |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
3,420,000.00 |
– |
3,420,000.00 |
Complete |
|
|
|
| 571 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT PWANI FYM, KEWA DEB AND SIRENDE PRIMARY SCHOOLS IN NAITIRI/KABUYEFWE WARD |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
4,190,960.00 |
– |
4,190,960.00 |
Complete |
|
|
|
| 572 |
Periodic Maintenance of Nzoia junction – Pwani- Mitua road3km |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 573 |
periodic Maintenance of Nasianda – Luungai 2km Road |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 574 |
periodic Maintenance of Nasianda – Luungai 2km Road |
TONGAREN |
NAITIRI/KABUYEFWE |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 575 |
Purchase of 1 acre land for sango village polytechnic |
BUMULA |
KHASOKO |
Sango village |
|
|
350,000.00 |
350,000.00 |
– |
Complete |
|
|
|
| 576 |
purchase of 1 acre land Namanze sec. School |
BUMULA |
KHASOKO |
Namanze |
|
|
350,000.00 |
350,000.00 |
– |
Complete |
|
|
|
| 577 |
purchase of 1/2 land for Maraba Primary school |
BUMULA |
KHASOKO |
Maraba |
|
|
200,000.00 |
200,000.00 |
– |
Complete |
|
|
|
| 578 |
Proposed construction of market stalls at Nasyanda |
BUMULA |
KHASOKO |
0 |
|
|
3,918,027.80 |
2,918,027.00 |
1,000,000.80 |
Complete |
|
|
|
| 579 |
Erection and completion of Namatotoa dispensary |
BUMULA |
KHASOKO |
Namatotoa |
|
|
4,067,298.80 |
3,227,638.00 |
570,000.00 |
Complete |
|
|
|
| 580 |
Periodic Maintenance of MCA Jnctn-lubunda-R.Nasianda-Makelo- R.sio road |
BUMULA |
KHASOKO |
0 |
|
|
7,542,436.00 |
6,295,791.00 |
1,246,645.00 |
Complete |
|
|
|
| 581 |
Erection and completion of Namusasi dispensary |
BUMULA |
KHASOKO |
Namusasi |
|
|
3,174,073.20 |
2,449,807.00 |
724,266.20 |
Complete |
|
|
|
| 582 |
Proposed erection and completion of 10no. Doors pitlatrine at Khasoko pri. |
BUMULA |
KHASOKO |
0 |
|
|
3,918,027.00 |
2,735,208.00 |
1,182,819.00 |
Complete |
|
|
|
| 583 |
Peridic maintenance of roads in Khasoko ward |
BUMULA |
KHASOKO |
0 |
|
|
9,004,478.50 |
– |
9,004,478.50 |
Complete |
|
|
|
| 584 |
DRILLING OF BOREHOLES AT LUBUNDA AND NAMANZE MARKET AND PROTECTION OF 2 SPRINGS |
BUMULA |
KHASOKO |
0 |
|
|
3,986,000.00 |
– |
3,986,000.00 |
Complete |
|
|
|
| 585 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT NAMANZE, BWALIRO AND LUBUNDA IN KHASOKO WARD |
BUMULA |
KHASOKO |
0 |
|
|
4,056,130.00 |
– |
4,056,130.00 |
Complete |
|
|
|
| 586 |
construction of Namanze health cente |
BUMULA |
KHASOKO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 587 |
Grading ,gravelling and culvert installation at mungore-lubanda-mianga junction 4.5KM |
BUMULA |
KHASOKO |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 588 |
Construction Ecosan Latrine-kaptanai dispensary |
SIRISIA |
NAMWELA |
Kaptanai dispensary |
|
|
250,000.00 |
250,000.00 |
– |
Complete |
|
|
|
| 589 |
construction of 2 door latrines at Toloso polytechnic |
SIRISIA |
NAMWELA |
Toloso polytechnic |
|
|
200,000.00 |
200,000.00 |
– |
Complete |
|
|
|
| 590 |
Equiping Kolani Dispensary |
SIRISIA |
NAMWELA |
0 |
|
|
500,000.00 |
500,000.00 |
– |
Complete |
|
|
|
| 591 |
Drilling of a borehole and construction of Tanks |
SIRISIA |
NAMWELA |
Kuafu |
|
|
2,820,602.00 |
2,250,132.00 |
570,470.00 |
Complete |
|
|
|
| 592 |
Periodic Mantainance of chwele girls – kuafu road |
SIRISIA |
NAMWELA |
0 |
|
|
7,377,832.00 |
6,382,894.00 |
994,938.00 |
Complete |
|
|
|
| 593 |
Digging piping & installation of 3tanks at Kikai water project |
SIRISIA |
NAMWELA |
Kikai |
|
|
2,317,500.00 |
2,085,750.00 |
231,750.00 |
0 |
|
|
|
| 594 |
Periodic mantainance of Kolani – wangwe road |
SIRISIA |
NAMWELA |
0 |
|
|
2,113,056.00 |
1,893,618.00 |
219,438.00 |
0 |
|
|
|
| 595 |
Periodic Maintenance of Menu Cattle Dip-Menu Coffee Factory Road |
SIRISIA |
NAMWELA |
Menu |
|
|
3,930,080.00 |
3,541,340.00 |
388,740.00 |
Complete |
|
|
|
| 596 |
PROTECTION OF 6NO. NAMWELA WATER SPRINGS |
SIRISIA |
NAMWELA |
0 |
|
|
927,000.00 |
– |
927,000.00 |
Complete |
|
|
|
| 597 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT NABEKI, NAMTOKHOLO, BUTUNDE AND SENGETETI PRIMARY SCHOOLS IN NAMWELA WARD |
SIRISIA |
NAMWELA |
0 |
|
|
5,411,680.00 |
– |
5,411,680.00 |
Complete |
|
|
|
| 598 |
Grading,Gravelling and culvert installation of wangwe road |
SIRISIA |
NAMWELA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 599 |
Rehabilitation of Boreholes in Butunde, Wapukha,Mlango,Kwafu,Kolani and Drilling of Munyanganyi,Khasinja |
SIRISIA |
NAMWELA |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 600 |
Bursary for needy cases |
KIMILILI |
KIBINGEI |
0 |
|
|
977,000.00 |
977,000.00 |
– |
Complete |
|
|
|
| 601 |
Bursary for needy cases |
KIMILILI |
KIBINGEI |
0 |
|
|
1,945,000.00 |
1,945,000.00 |
– |
Complete |
|
|
|
| 602 |
purchase of land for Chebukwabi Dispensary |
KIMILILI |
KIBINGEI |
0 |
|
|
435,000.00 |
435,000.00 |
– |
Complete |
|
|
|
| 603 |
purchase of 1 acre for Kitayi dispensary |
KIMILILI |
KIBINGEI |
Kitayi |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 604 |
construction of Mama Golda masafu bridge on river Kibingei Musima-bokoli bridge on river Kibisi |
KIMILILI |
KIBINGEI |
0 |
|
|
5,956,240.40 |
4,256,574.00 |
1,699,666.40 |
Complete |
|
|
|
| 605 |
purchase of 1 acre for Kibingei dispensary |
KIMILILI |
KIBINGEI |
0 |
|
|
800,000.00 |
800,000.00 |
– |
Complete |
|
|
|
| 606 |
Extension of Nzowasco pipeline |
KIMILILI |
KIBINGEI |
0 |
|
|
6,021,599.00 |
4,927,329.00 |
1,094,270.00 |
Complete |
|
|
|
| 607 |
Construction of twin ECDE Classroom at Namakhele Primary school |
KIMILILI |
KIBINGEI |
Namakhele |
|
|
3,187,761.20 |
– |
3,187,761.20 |
Complete |
|
|
|
| 608 |
Completion of the kibengei dispensary,fencing the dispensary and planting trees and construction of nurese house at daraja mungu dispensary |
KIMILILI |
KIBINGEI |
kibingei |
|
|
4,257,339.20 |
– |
4,257,339.20 |
Complete |
|
|
|
| 609 |
DRILLING OF KITAYI BOREHOLE |
KIMILILI |
KIBINGEI |
Kitayi |
|
|
1,972,000.00 |
– |
1,972,000.00 |
Complete |
|
|
|
| 610 |
DRILLING OF KIMILILI FYM BOREHOLE AND CONSTRUCTION OF 1 NO. WATER SPRING IN KIBINGEI WARD |
KIMILILI |
KIBINGEI |
Kimilili pri |
|
|
2,503,678.00 |
– |
2,503,678.00 |
Complete |
|
|
|
| 611 |
CONSTRUCTION OF 3NO. CLASSROOMS AT SAENYI, NAMAKHELE AND ALLAN BRADLEY PRIMARY SCHOOLS IN KIBINGEI WARD |
KIMILILI |
KIBINGEI |
Namakhele |
|
|
3,933,490.00 |
– |
3,933,490.00 |
Complete |
|
|
|
| 612 |
Purchase of 1 acre for Chebukwabi dispensary |
KIMILILI |
KIBINGEI |
Chebukwabi |
|
|
850,000.00 |
– |
850,000.00 |
Complete |
|
|
|
| 613 |
purchase of 1/2 acre land Namakhele dispensary. |
KIMILILI |
KIBINGEI |
Namakhele |
|
|
– |
– |
– |
Complete |
|
|
|
| 614 |
Grading ,gravelling Kundani-kolongolo friends-Kibisi river 3km |
KIMILILI |
KIBINGEI |
kibingei |
|
|
– |
– |
– |
Complete |
|
|
|
| 615 |
Grading ,gravelling Otando- Namakhele-Panyako-Onyamasi road 2.5 |
KIMILILI |
KIBINGEI |
kibingei |
|
|
– |
– |
– |
Complete |
|
|
|
| 616 |
Grading ,gravelling Naporora-Ndalila-Lutaso-Siuna 1.5 |
KIMILILI |
KIBINGEI |
kibingei |
|
|
– |
– |
– |
Complete |
|
|
|
| 617 |
Protection of Yonah Namuli water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Yona Namumali |
|
|
– |
132,192.00 |
(132,192.00) |
Complete |
|
|
|
| 618 |
Protection of makata water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Makata |
|
|
– |
132,750.00 |
(132,750.00) |
Complete |
|
|
|
| 619 |
Protection of Busonge A water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Busonge |
|
|
146,380.00 |
131,742.00 |
14,638.00 |
Complete |
|
|
|
| 620 |
Protection of Wakwabubi water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Wakwabubi |
|
|
144,380.00 |
129,942.00 |
14,438.00 |
Complete |
|
|
|
| 621 |
Protection of Lutaso water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Lutaso |
|
|
145,480.00 |
130,932.00 |
14,548.00 |
Complete |
|
|
|
| 622 |
Protection of Khalaba water spring |
KABUCHAI |
KABUCHAI/CHWELE |
Khalaba |
|
|
148,780.00 |
133,902.00 |
14,878.00 |
Complete |
|
|
|
| 623 |
Periodic maintenance of Wamunyokoli – Kibichori road |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
5,201,898.20 |
4,733,727.54 |
468,170.66 |
Complete |
|
|
|
| 624 |
Periodic Mantainanace of makokha junction chebunyinyi ACK Rd |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
3,115,542.51 |
2,606,239.00 |
509,303.51 |
Complete |
|
|
|
| 625 |
Periodic Maintenance of Sikusi- Namilama- Lwanda road |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
4,069,674.00 |
2,661,369.00 |
1,408,305.00 |
Complete |
|
|
|
| 626 |
Construction and protection of Namusimbi borehole |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
1,972,800.00 |
– |
1,972,800.00 |
0 |
|
|
|
| 627 |
Construction of 4NO water springs |
KABUCHAI |
KABUCHAI/CHWELE |
Munoko,Watitwa,Gilbert,Makhonge |
|
|
587,290.00 |
– |
587,290.00 |
Complete |
|
|
|
| 628 |
DRILLING OF NAKITUMBA(MATIBO) BOREHOLE WATER PROJECT |
KABUCHAI |
KABUCHAI/CHWELE |
Nakitumba |
|
|
2,179,640.00 |
– |
2,179,640.00 |
Complete |
|
|
|
| 629 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT MUKWEYA PRIMARY, LUFUTU SA, MATIBO FYM, SIRWA DEB, WALUKAYA DEB AND NAIRUBI DEB IN CHWELE/KABUCHAI WARD |
KABUCHAI |
KABUCHAI/CHWELE |
Lufutu,Matibo |
|
|
6,961,000.00 |
– |
6,961,000.00 |
Complete |
|
|
|
| 630 |
Grading and gravelling Namakhele –Nalondo |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 631 |
onstruction of ECDE 1 No Classroom in Makhonge S.A and a Toilet |
KABUCHAI |
KABUCHAI/CHWELE |
Makhonge |
|
|
– |
– |
– |
Complete |
|
|
|
| 632 |
Construction of Boda Boda sheds at Chwele Market |
KABUCHAI |
KABUCHAI/CHWELE |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 633 |
Construction of Korosiondet primary school ECDE classroom |
SIRISIA |
LWANDANYI |
Korosiondet |
|
|
900,000.00 |
900,000.00 |
– |
Complete |
|
|
|
| 634 |
Periodic Mantainance of sitabicha londo Rd |
SIRISIA |
LWANDANYI |
0 |
|
|
7,224,712.00 |
6,133,711.00 |
1,091,001.00 |
Complete |
|
|
|
| 635 |
Rehabilitation of 1 No borehole at Nambale |
SIRISIA |
LWANDANYI |
Nambale |
|
|
192,500.00 |
191,204.00 |
1,296.00 |
Complete |
|
|
|
| 636 |
Rehabilitation of 1 No borehole at Kabukara |
SIRISIA |
LWANDANYI |
Kabukara |
|
|
192,500.00 |
191,204.00 |
1,296.00 |
Complete |
|
|
|
| 637 |
Rehabilitation of 1 No borehole at Kaburiet |
SIRISIA |
LWANDANYI |
Kaburiet |
|
|
192,500.00 |
191,204.00 |
1,296.00 |
Complete |
|
|
|
| 638 |
Rehabilitation of 1 No borehole at Wamono |
SIRISIA |
LWANDANYI |
Wamono |
|
|
192,500.00 |
– |
192,500.00 |
Complete |
|
|
|
| 639 |
protection of Namawanga water spring project. |
SIRISIA |
LWANDANYI |
Namawanga |
|
|
200,000.00 |
190,000.00 |
10,000.00 |
Complete |
|
|
|
| 640 |
Construction and protection of John Omuse Water spring |
SIRISIA |
LWANDANYI |
John Omuse |
|
|
200,000.00 |
190,000.00 |
10,000.00 |
Complete |
|
|
|
| 641 |
Periodic Mantainance of Chebukuyi- komirial kimalilo Rd |
SIRISIA |
LWANDANYI |
0 |
|
|
10,741,368.00 |
8,488,024.00 |
2,253,344.00 |
Complete |
|
|
|
| 642 |
REHABILITATION OF 3 NO. BOREHOLES AND CONSTRUCTION OF 10 NO. WATER SPRINGS |
SIRISIA |
LWANDANYI |
0 |
|
|
2,499,921.00 |
– |
2,499,921.00 |
Complete |
|
|
|
| 643 |
DRILLING OF NASALA AND LURARE BOREHOLES |
SIRISIA |
LWANDANYI |
Nasala,Lurare |
|
|
3,540,800.00 |
– |
3,540,800.00 |
Complete |
|
|
|
| 644 |
DRILLING OF MACHAKHA BOREHOLE |
SIRISIA |
LWANDANYI |
0 |
|
|
1,782,000.00 |
– |
1,782,000.00 |
Complete |
|
|
|
| 645 |
CONSTRUCTION OF BODABODA SHEDS AT WAMONO, LWANDANYI, MACHAKHA, TULIENGE TAMULEGA, NAMBUYA SITABICHA AND KOROSIANDET |
SIRISIA |
LWANDANYI |
Wamono,Lwandanyi,Machakha |
|
|
– |
– |
2,756,979.00 |
Complete |
|
|
|
| 646 |
CONSTRUCTION OF 3 NO BODA BODA SHEDS AT TAMLEGA,KATOMEI AND MALAKISI AND 3 NO MAMA MBOGA SHEDS AT MALAKISI MARKET,LWANDANYI MARKET AND WAMONO MARKET |
SIRISIA |
LWANDANYI |
Tamlega,Ktomei |
|
|
– |
– |
– |
Complete |
|
|
|
| 647 |
construction of public toilets |
SIRISIA |
LWANDANYI |
wamono, lwandanyi and tulienge |
|
|
– |
– |
– |
Complete |
|
|
|
| 648 |
Construction of 08 ECDE Classrooms at Kaburuet, Chebukunyi, Kaprot, Namubila, Namawanga, Tulienge, Kibindoi, and Kapendo, |
SIRISIA |
LWANDANYI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 649 |
Purchase of 525 Desks for Eight ECDE Classes |
SIRISIA |
LWANDANYI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 650 |
protection of Skimbo water spring |
KANDUYI |
EAST SANGALO |
Skimbo |
|
|
147,158.00 |
147,158.00 |
– |
Complete |
|
|
|
| 651 |
protection of Mufule water spring |
KANDUYI |
EAST SANGALO |
Mufule |
|
|
162,818.00 |
162,818.00 |
– |
Complete |
|
|
|
| 652 |
protection of Namisi water spring |
KANDUYI |
EAST SANGALO |
Namisi |
|
|
141,968.00 |
141,968.00 |
– |
Complete |
|
|
|
| 653 |
protection of Opara water spring |
KANDUYI |
EAST SANGALO |
Opara |
|
|
142,619.00 |
142,619.00 |
– |
Complete |
|
|
|
| 654 |
protection of Fuchani water spring |
KANDUYI |
EAST SANGALO |
Fuchani |
|
|
142,619.00 |
142,619.00 |
– |
Complete |
|
|
|
| 655 |
protection of Dominico water spring |
KANDUYI |
EAST SANGALO |
Dominico |
|
|
162,818.00 |
162,818.00 |
– |
Complete |
|
|
|
| 656 |
Construction of one toilet at Sango ECDE |
KANDUYI |
EAST SANGALO |
Sango ECDE |
|
|
73,640.00 |
73,640.00 |
– |
Complete |
|
|
|
| 657 |
Construction of kachombo bridge |
KANDUYI |
EAST SANGALO |
Kachombo |
|
|
1,999,993.50 |
1,835,567.90 |
164,425.60 |
Complete |
|
|
|
| 658 |
Purchase of land for Napong’o dispensary |
KANDUYI |
EAST SANGALO |
Napong’o |
|
|
800,000.00 |
800,000.00 |
– |
Complete |
|
|
|
| 659 |
Construction and protection of water spring at Mabusi |
KANDUYI |
EAST SANGALO |
Mabusi |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 660 |
Construction and protection of water spring at Kere |
KANDUYI |
EAST SANGALO |
Kere |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 661 |
Construction and protection of water spring at Khamasa |
KANDUYI |
EAST SANGALO |
Khamasa |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 662 |
Construction and protection of water spring at Bubole |
KANDUYI |
EAST SANGALO |
Bubole |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 663 |
Construction and protection of water spring at Sango |
KANDUYI |
EAST SANGALO |
Sango |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 664 |
Construction and protection of water spring at Kiliswa |
KANDUYI |
EAST SANGALO |
Kiliswa |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 665 |
Construction and protection of water spring at Opora |
KANDUYI |
EAST SANGALO |
Opora |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 666 |
Construction and protection of water spring at Muchembi |
KANDUYI |
EAST SANGALO |
Muchembi |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 667 |
Construction and protection of water spring at Lukhuna |
KANDUYI |
EAST SANGALO |
Lukhuna |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 668 |
Construction and protection of water spring at Nabutola |
KANDUYI |
EAST SANGALO |
Nabutola |
|
|
84,610.00 |
64,726.00 |
19,884.00 |
Complete |
|
|
|
| 669 |
school empowerment programme |
KANDUYI |
EAST SANGALO |
0 |
|
|
790,000.00 |
790,000.00 |
– |
Complete |
|
|
|
| 670 |
Peridic mantainance of Mechimeru- Mutoto Wakhima road |
KANDUYI |
EAST SANGALO |
0 |
|
|
6,179,157.60 |
4,337,443.00 |
1,841,714.60 |
Complete |
|
|
|
| 671 |
Periodic mantainance of Mufule – Nabutola road |
KANDUYI |
EAST SANGALO |
0 |
|
|
6,804,966.00 |
3,097,101.00 |
3,707,865.00 |
Complete |
|
|
|
| 672 |
Periodic maintenance of roads in East Sang’alo ward |
KANDUYI |
EAST SANGALO |
0 |
|
|
13,308,964.20 |
– |
13,308,964.20 |
Complete |
|
|
|
| 673 |
PROTECTION OF 10 WATER SPRINGS IN EAST SANG’ALO WARD. |
KANDUYI |
EAST SANGALO |
0 |
|
|
1,100,000.00 |
– |
1,100,000.00 |
Complete |
|
|
|
| 674 |
POWER INSTALLATION AT MUMBULE DISPENSARY |
KANDUYI |
EAST SANGALO |
Mumbule |
|
|
487,486.40 |
– |
487,486.40 |
Complete |
|
|
|
| 675 |
CONSTRUCTION OF 1 NO.ECDE CLASSROOM AT KHAKULA AND MUSAKASA PRIMARY SCHOOLS IN EAST SANG’ALO WARD |
KANDUYI |
EAST SANGALO |
Khakula |
|
|
2,427,200.00 |
– |
2,427,200.00 |
Complete |
|
|
|
| 676 |
construction of Lutungu Foot Bridge |
KANDUYI |
EAST SANGALO |
lutungu- |
|
|
– |
– |
– |
Complete |
|
|
|
| 677 |
Periodic Maintenance of Sikalame Market-Mukhulu Market-Kuywa Stretch |
KANDUYI |
EAST SANGALO |
Sikalame |
|
|
– |
– |
– |
Complete |
|
|
|
| 678 |
Periodic Maintenance of Lutungu-Napongo-Lutungu Stretch |
KANDUYI |
EAST SANGALO |
lutungu- |
|
|
– |
– |
– |
Complete |
|
|
|
| 679 |
completion of Mechi-Meru maternity wing |
KANDUYI |
EAST SANGALO |
Mechimeru |
|
|
– |
– |
– |
Complete |
|
|
|
| 680 |
construction of mumbule matenity wing |
KANDUYI |
EAST SANGALO |
mumbule |
|
|
– |
– |
– |
Complete |
|
|
|
| 681 |
purchase of land for Chebinyiny ECDE |
MT. ELGON |
CHESIKAKI |
Chebinyiny |
|
|
400,000.00 |
400,000.00 |
– |
Complete |
|
|
|
| 682 |
purchase of land for Chemekerer ECDE |
MT. ELGON |
CHESIKAKI |
Chemekerer |
|
|
400,000.00 |
400,000.00 |
– |
0 |
|
|
|
| 683 |
Fencing of the 2 acres of land for Chebinyinyi & Chemekerer ECDE |
MT. ELGON |
CHESIKAKI |
0 |
|
|
170,000.00 |
170,000.00 |
– |
0 |
|
|
|
| 684 |
Purchase of land- TOROSO DISPENSARY |
MT. ELGON |
CHESIKAKI |
Malakisi |
|
|
450,000.00 |
450,000.00 |
– |
Complete |
|
|
|
| 685 |
Purchase of land-KAPCHEKUIE ECDE |
MT. ELGON |
CHESIKAKI |
Malakisi |
|
|
425,000.00 |
425,000.00 |
– |
Complete |
|
|
|
| 686 |
Purchase of land-CHEMA ECDE |
MT. ELGON |
CHESIKAKI |
Malakisi |
|
|
425,000.00 |
425,000.00 |
– |
Complete |
|
|
|
| 687 |
Purchase of land-Kaptama Health facility |
MT. ELGON |
CHESIKAKI |
Malakisi |
|
|
410,000.00 |
410,000.00 |
– |
Complete |
|
|
|
| 688 |
Periodic Maintenance of Embakasi -Mufungu road |
MT. ELGON |
CHESIKAKI |
0 |
|
|
3,908,643.00 |
2,834,066.00 |
1,074,577.00 |
Complete |
|
|
|
| 689 |
Periodic Maintenance of Tuikut Kiptaywa – Chemondi Road |
MT. ELGON |
CHESIKAKI |
0 |
|
|
6,250,080.00 |
4,493,256.00 |
1,756,824.00 |
Complete |
|
|
|
| 690 |
Periodic maintenance of Embakasi -Mutambo road |
MT. ELGON |
CHESIKAKI |
chesikaki |
|
|
4,044,920.00 |
3,866,784.00 |
178,136.00 |
Complete |
|
|
|
| 691 |
Periodic Maintenance of Bukonoi Marigo road |
MT. ELGON |
CHESIKAKI |
chesikaki |
|
|
4,997,676.00 |
3,790,917.00 |
1,206,759.00 |
Complete |
|
|
|
| 692 |
Rehabilitation of Chesikaki water supply project |
MT. ELGON |
CHESIKAKI |
chesikaki |
|
|
4,699,508.00 |
4,699,508.00 |
– |
0 |
|
|
|
| 693 |
Peridic maintenance of roads in Chesikaki ward |
MT. ELGON |
CHESIKAKI |
chesikaki |
|
|
13,546,220.00 |
– |
13,546,220.00 |
Complete |
|
|
|
| 694 |
Construction of 5 no Maternity wing in the following dispensariesKimama,Chesikaki,Tuikut,Kapkoto and Marigo |
MT. ELGON |
CHESIKAKI |
Mrigo,chesikaki |
|
|
– |
– |
– |
Complete |
|
|
|
| 695 |
CONSTRUCTION OF WATER PIPELINE EXTENSION FOR CHESIKAKI WATER PROJECT |
MT. ELGON |
CHESIKAKI |
chesikaki |
|
|
4,508,000.00 |
– |
4,508,000.00 |
Complete |
|
|
|
| 696 |
CONSTRUCTION OF 2NO. CLASSROOMS AND TOILET AT KIMABOLE AND TOROSO POLYTECHNIC IN CHESIKAKI WARD |
MT. ELGON |
CHESIKAKI |
kimabole |
|
|
5,819,220.00 |
– |
5,819,220.00 |
Complete |
|
|
|
| 697 |
Construction of 06 ECDE Classrooms at 1. Chesikaki FYM 2. Chesiywo 3. Chemondi S.A 4. Kabero P.R 5. Kimerin and 6. Bukonoi |
MT. ELGON |
CHESIKAKI |
Chesiyo,Kabero |
|
|
– |
– |
– |
Complete |
|
|
|
| 698 |
Grading and Gravelling 3 km Mulukhu – Melon – Kapkoto Road |
MT. ELGON |
CHESIKAKI |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 699 |
Periodic Maintenance of Chebunyinyi road |
BUMULA |
TUUTI MARAKARU |
0 |
|
|
997,000.00 |
997,000.00 |
– |
Complete |
|
|
|
| 700 |
Bursary for needy cases |
BUMULA |
TUUTI MARAKARU |
0 |
|
|
607,840.00 |
607,840.00 |
– |
Complete |
|
|
|
| 701 |
Repair of 1no. Water pump at matongi |
BUMULA |
TUUTI MARAKARU |
Matongi |
|
|
450,000.00 |
294,580.00 |
155,420.00 |
Complete |
|
|
|
| 702 |
Repair of 1no. Water pump at Wanjala |
BUMULA |
TUUTI MARAKARU |
Wanjala |
|
|
– |
– |
– |
0 |
|
|
|
| 703 |
Repair of 1no. Water pump at Maocho |
BUMULA |
TUUTI MARAKARU |
Maocho |
|
|
– |
– |
– |
0 |
|
|
|
| 704 |
Repair of 1no. Water pump at Kimukungi |
BUMULA |
TUUTI MARAKARU |
Kimukungi |
|
|
– |
– |
– |
0 |
|
|
|
| 705 |
Opening, grading,and laying of culverts on lumasa matongi Rd |
BUMULA |
TUUTI MARAKARU |
0 |
|
|
7,200,000.00 |
6,933,135.00 |
266,865.00 |
Complete |
|
|
|
| 706 |
Grading ,gravelling & laying of culverts of makutano – maporomoko rd |
BUMULA |
TUUTI MARAKARU |
0 |
|
|
6,850,844.00 |
3,286,395.00 |
3,564,449.00 |
Complete |
|
|
|
| 707 |
Periodic Maintenance of Kumbuka- Kikwechi polytechnic road |
BUMULA |
TUUTI MARAKARU |
0 |
|
|
5,721,584.00 |
4,926,120.00 |
795,464.00 |
Complete |
|
|
|
| 708 |
construction of Nabukhisa dispensary |
BUMULA |
TUUTI MARAKARU |
Nabukhisa |
|
|
2,571,511.00 |
– |
2,571,511.00 |
Complete |
|
|
|
| 709 |
DRILLING OF BUTIELI DISPENDARY AND LUMASA BOREHOLE |
BUMULA |
TUUTI MARAKARU |
Butiele,Lumasa |
|
|
3,222,080.00 |
– |
3,222,080.00 |
Complete |
|
|
|
| 710 |
DRILLING OF KAKICHUMBA AND MAYANJA BOREHOLES IN TUUTI MARAKARU WARD |
BUMULA |
TUUTI MARAKARU |
Mayanja,Kakichuma |
|
|
3,907,483.20 |
– |
3,907,483.20 |
Complete |
|
|
|
| 711 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AT LUMASA, BUEMA, BUKUSU, MUNGETI, SITOMA AND NAKAYONJO PRIMARY IN TUUTI/MARAKARU WARD |
BUMULA |
TUUTI MARAKARU |
Buema,Sitoma,Lumasa |
|
|
7,487,800.00 |
– |
7,487,800.00 |
Complete |
|
|
|
| 712 |
Elite-Namawanga-mayanja road |
BUMULA |
TUUTI MARAKARU |
Mayanja |
|
|
– |
– |
– |
Complete |
|
|
|
| 713 |
Construction of 5no classrroms 1. Namikelo Primary 2.Bukananachi Primary 3.Maliki Primary 4. Kimukungi Primary 5. Kakichuma primary |
BUMULA |
TUUTI MARAKARU |
1. Namikelo Primary 2.Bukananachi Primary 3.Maliki Primary 4. Kimukungi Primary 5. Kakichuma primary |
|
|
– |
– |
– |
Complete |
|
|
|
| 714 |
Construction of 1 No bodaboda shed at Tabani |
TONGAREN |
NDALU |
Tabani |
|
|
863,968.00 |
699,814.00 |
164,154.00 |
Complete |
|
|
|
| 715 |
Construction of 2 No bodaboda shed at Ndalu |
TONGAREN |
NDALU |
Ndalu |
|
|
– |
– |
– |
Complete |
|
|
|
| 716 |
Construction of 1 No bodaboda shed at T- junction |
TONGAREN |
NDALU |
T-Junction |
|
|
– |
– |
– |
Complete |
|
|
|
| 717 |
Bursary for needy cases |
TONGAREN |
NDALU |
0 |
|
|
700,000.00 |
700,000.00 |
– |
Complete |
|
|
|
| 718 |
Installation of culverts at wekuke – waliombo drift |
TONGAREN |
NDALU |
waliombo |
|
|
7,103,492.00 |
5,961,276.00 |
1,142,216.00 |
Complete |
|
|
|
| 719 |
Construction of 1 No water springs at Sadam |
TONGAREN |
NDALU |
Sadam |
|
|
282,368.55 |
237,819.00 |
44,549.55 |
Complete |
|
|
|
| 720 |
Construction of 1 No water springs at Sakong |
TONGAREN |
NDALU |
Sakong |
|
|
282,368.55 |
237,819.00 |
44,549.55 |
Complete |
|
|
|
| 721 |
Construction of 1No water springs at Andanda |
TONGAREN |
NDALU |
Andanda |
|
|
282,368.55 |
237,819.00 |
44,549.55 |
Complete |
|
|
|
| 722 |
Construction of1No bodaboda sheds at Bunambo |
TONGAREN |
NDALU |
Bunambo |
|
|
270,030.30 |
269,771.00 |
259.30 |
Complete |
|
|
|
| 723 |
Construction of 1No bodaboda sheds at Ndalu junction |
TONGAREN |
NDALU |
Ndalu junction |
|
|
270,030.30 |
269,771.00 |
259.30 |
Complete |
|
|
|
| 724 |
Purchase of land for Buyofu pri. |
TONGAREN |
NDALU |
0 |
|
|
1,100,000.00 |
1,100,000.00 |
– |
Complete |
|
|
|
| 725 |
Periodic Mantainance of Mulirodip junction-musembe pri. |
TONGAREN |
NDALU |
0 |
|
|
8,848,770.00 |
6,908,827.00 |
1,939,943.00 |
Complete |
|
|
|
| 726 |
Peridic maintenance of roads in Ndalu/Tabani ward(Milimani pag-sokomjinga-tali bridge road2.7km,Maisha mapya-wanyama –lavisa cattle dip road2.25km) |
TONGAREN |
NDALU |
0 |
|
|
12,463,185.00 |
– |
12,463,185.00 |
Complete |
|
|
|
| 727 |
CONTRUCTION OF 4NO. WATER SPRINGS |
TONGAREN |
NDALU |
0 |
|
|
788,368.00 |
– |
788,368.00 |
Complete |
|
|
|
| 728 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AND PIT LATRINE AT MUSANGURA AND NZOIA PRIMARY SCHOOLS IN NDALU WARD |
TONGAREN |
NDALU |
0 |
|
|
3,536,770.00 |
– |
3,536,770.00 |
Complete |
|
|
|
| 729 |
Purchase of 1 acre for Nzoia F Y M primary school |
TONGAREN |
NDALU |
Nzoia |
|
|
850,000.00 |
– |
850,000.00 |
Complete |
|
|
|
| 730 |
Mwalimu kisika–Tabani RC scholl-T junction road |
TONGAREN |
NDALU |
ndalu |
|
|
– |
– |
– |
Complete |
|
|
|
| 731 |
Purchase of 5 acres of land for expansion of Ndalu market |
TONGAREN |
NDALU |
ndalu |
|
|
– |
– |
– |
Complete |
|
|
|
| 732 |
Constructing one classroom at Sirisia polytechnic |
WEBUYE WEST |
MISIKHU |
Sirisia |
|
|
970,000.00 |
970,000.00 |
– |
Complete |
|
|
|
| 733 |
Purchase of land–ST JOSEPHS MANANI POLY |
WEBUYE WEST |
MISIKHU |
|
|
|
1,900,000.00 |
1,900,000.00 |
– |
Complete |
|
|
|
| 734 |
grading and gravelling of punda-masindejunction Rd |
WEBUYE WEST |
MISIKHU |
0 |
|
|
2,114,448.00 |
1,829,376.00 |
285,072.00 |
Complete |
|
|
|
| 735 |
Periodic maintenance of lugulu sec.school-khwatenge-pst.shivoko |
WEBUYE WEST |
MISIKHU |
0 |
|
|
4,283,664.85 |
2,908,039.00 |
1,375,625.85 |
Complete |
|
|
|
| 736 |
Renovation of Kituny Dispensary |
WEBUYE WEST |
MISIKHU |
0 |
|
|
1,612,465.00 |
1,485,524.25 |
126,940.75 |
Complete |
|
|
|
| 737 |
Periodic mantainance of Saya kombo-Indienyi wanyama- saratuki simon road |
WEBUYE WEST |
MISIKHU |
0 |
|
|
10,127,061.00 |
9,200,132.00 |
926,929.00 |
0 |
|
|
|
| 738 |
Peridic maintenance of roads in Misikhu ward(Makhese-lazaro-kituni road 2.88km) |
WEBUYE WEST |
MISIKHU |
0 |
|
|
8,681,792.20 |
– |
8,681,792.20 |
Complete |
|
|
|
| 739 |
CONSTRUCTION AND PROTECTION OF MISIKHU WATER SPRINGS |
WEBUYE WEST |
MISIKHU |
0 |
|
|
918,256.00 |
– |
918,256.00 |
0 |
|
|
|
| 740 |
CONSTRUCTION OF 1NO. ECDE CLASSROOM AND 1NO. PIT LATRINE AT SIRISIA, CHENGOLI AND MISIKHU RC PRIMARY SCHOOLS AND SIRISIA VOCATIONAL TRAINING CENTRE IN MISIKHU WARD |
WEBUYE WEST |
MISIKHU |
0 |
|
|
5,891,400.00 |
– |
5,891,400.00 |
Complete |
|
|
|
| 741 |
construction of 2 NO door pit latrines |
WEBUYE WEST |
MISIKHU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 742 |
Drilling and Equiping of 02 Boreholes at Kituni secondary school and lugulu community |
WEBUYE WEST |
MISIKHU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 743 |
Periodic maintenance of Wenyila-Kituni-Bunjusi-Daraja mbili road. 4Km |
WEBUYE WEST |
MISIKHU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|
| 744 |
Dozing ,Grading and Gravelling of Matala-Nkhabala-Lukhuna Road |
WEBUYE WEST |
MISIKHU |
0 |
|
|
– |
– |
– |
Complete |
|
|
|